Bechtel to aid Browns Ferry restart

3 November 2002


Bechtel began work in October on a $300 million five-year contract to provide restart services for Browns Ferry 1. The company also previously provided engineering and technical services during the restart of Browns Ferry 2 and 3.

Browns Ferry 1 has been in layup since 1985. Restart is expected to take five years and cost up to $1.8 billion. The project was agreed by the board of directors of plant owners Tennessee Valley Authority (TVA) in May. TVA said the restart will make good business sense and will enable the company to provide reliable power in the Tennessee area.



Privacy Policy
We have updated our privacy policy. In the latest update it explains what cookies are and how we use them on our site. To learn more about cookies and their benefits, please view our privacy policy. Please be aware that parts of this site will not function correctly if you disable cookies. By continuing to use this site, you consent to our use of cookies in accordance with our privacy policy unless you have disabled them.