The Team Korea consortium led by Korea Hydro & Nuclear Power (KHNP) have issued a joint pledge to complete the Dukovany nuclear power project in the Czech Republic on time and within budget. The pledge was endorsed by key consortium partners, including KHNP, KEPCO E&C, KEPCO KPS, KEPCO Nuclear Fuel, and Doosan Enerbility.

In a joint statement, Team Korea said, “Our commitment to completing the project on schedule and building the safest possible nuclear power plant within the agreed budget and timeframe is our foremost, non-negotiable principle. With KHNP at the centre, we will stand firmly united as one team and live up to the public’s expectations and trust.”

This follows the collapse of construction subcontract talks with the Daewoo E&C–Doosan Enerbility consortium. Talks broke down after 91 rounds of negotiations over a 15-month period. Daewoo E&C pushed back against KHNP’s insistence on a strict lump-sum, fixed-price contract, arguing it unfairly shifted the financial burden of increased work volumes and unfinished design changes onto the builders.

In the wake of the collapse and termination of the construction cooperation agreement earlier in November, KHNP activated an emergency response system alongside South Korea’s Ministry of Trade, Industry & Energy to keep critical groundwork moving while a replacement builder is selected.

Consortium leaders confirmed that engineering design, reactor and turbine equipment supply, nuclear fuel delivery, and commissioning preparations are proceeding smoothly under the main contract signed in June 2025. The project, for KRW26–27 trillion ($18–$19.4bn), involves building two 1,000-MWe APR1000 reactors (units 5&6) at the existing Dukovany site.

A January 2027 briefing is scheduled for prospective replacement construction bidders. The target date to apply for the construction permit and open replacement contractor bidding is April, with the planned selection of the new construction contractor (Doosan Enerbility remains eligible to rebid) set for July. Site preparation is expected to begin in January 2028 with full-scale construction starting in November 2029. The target window for commercial operations is the late 2030s.

Despite Team Korea’s unified front, the dispute faces domestic pushback in South Korea. Lawmakers from both ruling and opposition parties on the National Assembly’s trade and energy committee are pushing for a parliamentary hearing to review KHNP’s handling of the contract termination and cost assessments.

In its joint statement, Team Korea emphasised that the Dukovany project is a key national initiative that will drive future energy security and industrial cooperation between the two countries. The team stressed that the overall schedule remains on track. It said early-stage critical work, including detailed engineering, the supply of major equipment and nuclear fuel, and commissioning and maintenance, is proceeding as planned.

Team Korea said: “The construction sector has also activated an emergency response system and is faithfully carrying out essential duties. We plan to quickly establish a new partnership with proven companies to ensure uninterrupted continuity of the project.”