Fermi America’s planned energy hub in Texas, Project Matador, is facing problems. According to Bloomberg, Fermi’s quarterly filing has confirmed the departure of its top nuclear executive and a one-year delay for its planned nuclear reactors. These setbacks accompany major customer shifts, regulatory risks, and ongoing leadership turmoil.
Project Matador, officially named the President Donald J Trump Advanced Energy and Intelligence Campus, is a massive, first-of-its-kind multi-billion-dollar private infrastructure hub being developed on 7,500-8,400 acres in Carson County, Texas (northeast of Amarillo). It is designed to be the world’s largest artificial intelligence (AI) data centre and energy co-location campus and is located adjacent to the DOE’s Pantex Plant.
The project aims to solve AI’s immense electricity demand by constructing a completely private, “behind-the-meter” hypergrid that combines massive fossil fuel generation, renewable energy, and nuclear power to operate entirely independently of the traditional Texas power grid.
The scale of energy production planned for Project Matador is unprecedented for a private campus, scaling up to a targeted 17 GWe of gross capacity: The foundation of its immediate power relies on what is projected to be the largest gas-fired power plant in the US, with 93 turbines generating over 5,100 MWe of dispatchable capacity.
Four proposed Westinghouse AP1000 nuclear reactors (designated as Project Matador Nuclear units 1–4) are planned to provide 4.4 GWe of zero-carbon baseload energy. Extensive utility-scale solar arrays and battery energy storage systems are being integrated to act as bridge capacity. Rather than using energy-intensive motorised fans or traditional wet cooling towers, the plant will use passive, hyperbolic natural-draft cooling towers hundreds of feet tall to leverage the natural West Texas wind. The site is being built on Texas Tech University land under a 99-year lease.
Chief Nuclear Construction Officer Mesut Uzman departed Fermi in October, pushing the commissioning of the AP1000 reactors to 2034-2037 – a one-year later than previous estimates and two years behind original goals. Uzman had been hired in 2025 to lead the nuclear part of Project Matador, because of his work delivering reactors in China and the United Arab Emirates.
Fermi terminated its initial $6.5bn binding customer agreement while landing a $200m upfront commitment from an unnamed AI hyperscaler for 600 MWe of capacity, alongside pending construction and materials agreements. The pre-revenue company posted a wider-than-expected third-quarter net loss of $141.6m driven largely by $142.2m in administrative costs.
The company cited escalating public backlash, local moratoria, and legislative restrictions targeting data centres in Texas and nationwide as threats to project scope and timelines. “The implementation of moratoria and new requirements and restrictions could increase costs, delay or reduce planned data centre infrastructure investments, limit the size and location of data centres, cause tenants to shift planned development to other jurisdictions, or otherwise constrain the deployment or expansion of data centre infrastructure by our tenants,” the company said in the filing.
These operational delays coincide with severe governance friction, including calls from ousted co-founder and former CEO Toby Neugebauer to sell the company following a shareholder vote to remove former Texas Governor Rick Perry from the board.
Neugebauer accused Fermi of falsely reporting his termination and is now pushing for a sale or a strategic partnership. He said that more than 61% of shareholders had rejected Perry’s re-election to the board.
Neugebauer said he had proposed selling or partnering with Fermi in May, when valuations ranged from $10-20bn. He said the board rebuffed interested banks and has not run the process. He noted that Fermi stock has fallen significantly and that new shares now raise far less capital. Neugebauer also pointed to changes in Fermi’s bylaws that are affecting the company now and questioned how the board is executing its tenant strategy.
Fermi now plans to commission one Westinghouse reactor a year from 2034 to 2037. In its last quarterly filing, it said it was targeting 2033 through 2036, while its original plan called for the first unit in 2032.