Summer 2&3 delays could cost AP1000 new-build project more than $1.2 billion

3 October 2014


Preliminary revised cost estimates provided by the consortium building the two-unit AP1000 nuclear reactors at VC Summer in Jenkinsville, South Carolina could add more than $1.2 billion on the cost of the project, according to 55% owner South Carolina Electric & Gas.

The cost estimates are actually based on preliminary schedule revisions received in August to the effect that unit 2 would be completed in late 2018-early 2019, and unit 3 would be completed 12 months later. This is about a year later than predictions given in November 2013.

The construction consortium consists of Westinghouse and Chicago Bridge & Iron.

SCE&G said that the delays, which it blames partly on late delivery of structural sub-moduls, have increased costs for non-firm and non-fixed scopes of work amounting to $660 million for its 55% stake. It also said that that figure was presented in 2007 dollars, and excludes some other costs.

SCE&G is currently working on a revised construction schedule of both units but did not say when it would be completed.

It said that the schedule, cost estimates are under review by SCE&G and state-owned utility Santee Cooper, which owns the other 45% of the project. "Neither SCE&G nor Santee Cooper has accepted financial responsibility for any project cost impact associated with these delays."

 


Picture: Bottom of three containment rings placed on containment vessel bottom head, VC Summer 2, June 2014. Picture from SCE&G



Privacy Policy
We have updated our privacy policy. In the latest update it explains what cookies are and how we use them on our site. To learn more about cookies and their benefits, please view our privacy policy. Please be aware that parts of this site will not function correctly if you disable cookies. By continuing to use this site, you consent to our use of cookies in accordance with our privacy policy unless you have disabled them.