Czech power group ÄŒEZ has become a shareholder in UK-based Rolls-Royce SMR. The gradual takeover of a one-fifth share of the company has now been approved by regulators. The companies will cooperate in the development of small modular reactors (SMRs), ÄŒEZ spokesman Ladislav KÅ™Ă­Å¾ announced. Rolls-Royce SMR was selected in September 2024 as the preferred supplier for the development and construction of a number of SMRs by the Czech government from a shortlist of seven companies.

The first SMR is expected to be built in the first half of the 2030s at the TemelĂ­n NPP. The agreement on strategic cooperation, which also provided for the purchase of about 20% of Rolls-Royce SMR, was signed by representatives of both companies in October 2024. In the longer term, ÄŒEZ plans to build SMRs with a total output of 3 GWe by 2050. These should be used primarily for heat supply and should be sited in the territory of current coal-fired power plants, for example in PrunĂ©Å™ov or DÄ›tmarovice.

Czech Prime Minister Petr Fiala described the construction of SMRs as a significant development, which will contribute to increasing energy security and self-sufficiency.

The Rolls-Royce SMR design is a three loop PWR with an output of 470 MWe derived from 1,358 MWt. The Rolls-Royce SMR concept is centred on modularisation of reliable and proven technology, allowing maximum use of the factory environment to combine standard components with advanced manufacturing techniques. The factory-built modularisation approach is expected to drastically reduce the amount of on-site construction while its compact footprint and modular design means it can be located alongside energy intensive industrial processes.

The Czech Republic currently gets about one-third of its electricity from four VVER-440 units at Dukovany NPP, which began operating between 1985 and 1987, and the two VVER-1000 units at TemelĂ­n NPP, which began operation in 2000 and 2002. In July, Korea Hydro & Nuclear Power (KHNP) was named the preferred bidder for up to four new units at Dukovany with the target of the first unit entering commercial operation in 2038.