Unit 8 of the Tianwan NPP in Lianyungang, East China’s Jiangsu Province, which is being built in China according to the Russian VVER-1200 project, is preparing to load nuclear fuel following completion of hot testing.

“The successful completion of the hot tests confirmed the safe and efficient operation of the equipment and technological systems,” said Alexey Bannik, Vice President for Projects in China and Promising Projects at Atomstroyexport (part of Rosatom). “We have reached the finish line in preparing the power unit for physical launch. Next, the main and auxiliary equipment of the first and second circuits will have to be audited, after which the approval of the supervisory authority for fuel loading will be obtained.”

Rosatom’s Fuel Division, TVEL supplied nuclear fuel for the initial core of Tianwan 8 as well as a number of fuel reserve assemblies. The fuel was manufactured at the Novosibirsk Chemical Concentrates Plant (NZKhK – Novosibirskii Zavod KhimConsentratov). Future fuel manufacturing for the VVER-1200 units is planned to be localised at the Yibin fuel plant in Sichuan Province.

The contract for the supply of nuclear fuel for Tianwan 7&8 was signed in July 2019 between TVEL and Chinese customers represented by Sunen Nuclear Energy Corporation and China Nuclear Energy Industry Corporation (both part of China National Nuclear Corporation – CNNC).

“In fulfilling this contract with Chinese partners, we achieved record volumes of nuclear fuel supplies to one country,” said Anton Ivanov, Vice President for Commerce & International Business at TVEL. “Since the end of 2025, three VVER-1200 cores have been delivered for Tianwan units 7&8 and for unit 3 of the Xudabao NPP. By the end of 2026, the initial load for Xudabao 4 will be manufactured and delivered to the customer.”

After commissioning unit 8, Tianwan NPP will become the world’s largest nuclear plant and will rank as one of the ten most powerful power plants in the world, second only to the largest hydroelectric power plants in China and South America.

In 2018, Russia and China signed four agreements, including for the construction of two VVER-1200 reactors for Tianwan units 7&8. Construction of unit 7 began in May 2021, and unit 8 in February 2022. Tianwan 7 was connected to the grid in October and is scheduled to be commissioned later this year followed by Tianwan 8 in 2027. Tianwan 1-4, with VVER-1000 reactors, commissioned between 2007 and 2018, are already in operation. Units 5&6 with Chinese ACPR-1000s were commissioned in 2020 and 2021.

With all eight units in operation, the total capacity of the station will be 9,138 MWe, making it the world’s largest nuclear station by installed capacity. It is expected to reduce carbon dioxide emissions by 57.4m tonnes a year.

The Tianwan NPP is also the basis for China’s first industrial nuclear steam supply project, Heqi No1, which uses secondary-circuit steam from Tianwan 3&4 to supply industrial steam through an independent heat-exchange system to the Xuwei petrochemical industrial base about 23 kilometres away.