Torness 1 enters maintenance outage

14 February 2014


On 7 February Scotland's Torness 1 advanced gas-cooled reactor (AGR) was brought offline for a planned maintenance outage to perform maintenance work costing £30 million in total. The scope of work includes replacing three generator transformer phases, each weighing 250 tonnes, turbine rotor and generator rotor exchanges.

Another job is the first-of-a-kind replacement of the electrical drives for the reactor gas circulators.

In addition, many key components are being inspected, including reactor internals, fuel channels, boilers, steam pipes, and electrical and control systems.

More than 13,000 separate work items are scheduled. Site staff numbers will double; 500 specialist workers are being brought in to help out.

In August 2013 Torness station (consisting of two units, 583 and 592 net MWe nominal full load), generated 200 TWh since start of operation in 1988. Like Hinkley B, Hunterston and Heysham B, both Torness units are refuelled online, at low power, unlike Dungeness B, Hartlepool and Heysham A reactors, which must be shut down to refuel.

 

Picture: Staff manoeuvre a 30-tonne low-pressure steam crossover pipe from the Torness 1 turbine.



Privacy Policy
We have updated our privacy policy. In the latest update it explains what cookies are and how we use them on our site. To learn more about cookies and their benefits, please view our privacy policy. Please be aware that parts of this site will not function correctly if you disable cookies. By continuing to use this site, you consent to our use of cookies in accordance with our privacy policy unless you have disabled them.