Russia to start testing equipment for large lead-cooled fast reactor

2 February 2024


Russia’s Siberian Chemical Plant (SCC part of Rosatom fuel company TVEL) plans in April 2026 to begin testing a small-scale model of the steam generator for the planned large-scale lead-cooled fast reactor – the BR-1200. This will be an industrial, more powerful version of the experimental Brest-OD-300, under construction at SCC as part of the pilot demonstration power complex (ODEK - Opitno Demonstratsionovo Energo-Kompleksa), which is part of the Breakthrough (Proryv) project intended to demonstrate closed fuel cycle technology.

The lead circuit parameters in the BR-1200 test bench – a lead temperature 350-550°C, and nominal lead coolant consumption of 134 kg per second – will be specified during design. It is expected that construction of the test bench will begin this year for completion in March 2026 and commissioning the following month. [The BR-1200 is not to be confused with the BN-1200 sodium-cooled fast reactor which is to be built at unit 5 of the Beloyarsk NPP].

The technical design of the test bench was developed by the NA Dollezhal Scientific Research & Design Institute of Power Engineering (NIKIET which earlier developed a model for the Brest-300. Russian scientists, according to Rosatom, have already prepared a technical proposal for a high-power reactor unit with lead coolant.

SCC has been responsible for implementing the ODEK project since 2011 which will also include a module for fabrication and refabrication of nuclear fuel (MFR) and a module for reprocessing irradiated fuel. The MFR is already almost completed and planned for commissioning this year. Construction of the Brest-300 began in 2021 and the launch is planned for 2027-2029. Construction of the reprocessing unit planned for 2025-2026 for commissioning in 2030.

Rosatom Director General Alexey Likhachev told Russia-24: “I think that in 2028-2029 we will launch Brest as a reactor and the whole complex, as an industrial unit. But before that, we will begin building new fast neutron reactors in the Russian Federation."


Image: Installation of equipment at the BREST-OD-300 reactor (courtesy of Rosatom)



Privacy Policy
We have updated our privacy policy. In the latest update it explains what cookies are and how we use them on our site. To learn more about cookies and their benefits, please view our privacy policy. Please be aware that parts of this site will not function correctly if you disable cookies. By continuing to use this site, you consent to our use of cookies in accordance with our privacy policy unless you have disabled them.