The UK Nuclear Installations Inspectorate (NII) has confirmed that BNFL has satisfactorily closed out the recommendations of a report on the control and supervision of operations at Sellafield, published in February 2000.

In response to the report, which contained 28 recommendations, Sellafield management developed a three-year plan

containing 41 key objectives. A project team was established to lead the implementation, and ensure that best practices identified in some areas of operations were spread across the whole site.

Key achievements include:

• The creation of a single

safety management system at Sellafield, with roles

and responsibilities clearly

identified.

• Creating the post of director

  Sellafield site, with full accountability for safety and operations across the site.

• Major changes to the BNFL organisation from board level down, which refreshed and strengthened the organisation at all levels and provided clear lines of accountability.

• Implementation of robust independent audit and review arrangements, through the use of external groups, and the establishment of corporate independent inspectors and independent compliance advisors.

• Focused training to enhance behavioural skills and

attitudes through implementation of clear standards and expectations.

BNFL chief executive Norman Askew said: "We have now successfully made the transformation we promised to all our stakeholders."



Privacy Policy
We have updated our privacy policy. In the latest update it explains what cookies are and how we use them on our site. To learn more about cookies and their benefits, please view our privacy policy. Please be aware that parts of this site will not function correctly if you disable cookies. By continuing to use this site, you consent to our use of cookies in accordance with our privacy policy unless you have disabled them.