Mochovce start-up

30 April 1998


Commissioning of Mochovce 1 should begin this summer according to plant officials. Pre-start testing has now reached the half-way stage. Following a further phase of tests and adjustments, lasting about three months, fuel loading will take place with the commissioning scheduled for 21 July. The general equipment supplier for the project is Skoda Prague. Siemens, Framatome and two Russian firms are also involved. The second Mochovce unit is to start up next year.



Privacy Policy
We have updated our privacy policy. In the latest update it explains what cookies are and how we use them on our site. To learn more about cookies and their benefits, please view our privacy policy. Please be aware that parts of this site will not function correctly if you disable cookies. By continuing to use this site, you consent to our use of cookies in accordance with our privacy policy unless you have disabled them.