Brunswick to be uprated

3 July 2002


Carolina Power & Light has received approval from the NRC to increase the generating capacity at its Brunswick 1 and 2 reactors by 15% each. Work will begin immediately at unit 1, increasing capacity from 841MWe to 958MWe, while work on unit 2 will start in 2003, raising its capacity from 835MWe to 951MWe.



Privacy Policy
We have updated our privacy policy. In the latest update it explains what cookies are and how we use them on our site. To learn more about cookies and their benefits, please view our privacy policy. Please be aware that parts of this site will not function correctly if you disable cookies. By continuing to use this site, you consent to our use of cookies in accordance with our privacy policy unless you have disabled them.