AREVA-Siemens wins nuclear I&C contract for China's Fuqing 5&6

10 December 2013


AREVA, in consortium with Siemens has won a contract to supply the instrumentation and control systems for units 5&6 of the Fuqing nuclear power plant in China.

China Nuclear Power Engineering, a subsidiary of China National Nuclear Corporation will manage construction of the two 1000 MWe reactors, which is due to begin in 2014 and 2015.

Fuqing 5&6 will use the AREVA TELEPERM-XS digital safety I&C system, which is currently in use in 14 different reactor designs across 16 different countries.

The recent Chinese contract builds on over 30-years of cooperation between France and China in civil nuclear power. AREVA-Siemens has supplied I&C systems for five of China's 18 operational reactors: Tianwan 1&2, Ling Ao 3&4 and Qinshan 1. The consortium also has agreements covering the supply of I&C systems for Fuqing 3&4 and Taishan 1&2, currently under construction in China, as well as for the the Russian-designed VVER-1000 reactors at Tianwan 3&4.

The TELEPERM-XS technology

The TELEPERM-XS technology is currently licensed in France, China, Finland, Germany, the United States, Russia, Brazil, Argentina, Spain, Sweden, Switzerland, Hungary, Bulgaria and Slovakia. Some 80 TELEPERM-XS systems have been supplied or are currently installed, according to AREVA.

The technology can be used in both new-build and upgrade markets. In 2011, unit 1 at Duke Energy's Oconee Nuclear Station became the first reactor in the US to upgrade from 1970s-era analogue instrumentation and control to a digital reactor protection system (RPS), engineered safety (ES) system, and nuclear instrumentation system (NIS).

The TELEPERM-XS I&C system aims to avoid system faults and errors through a modular design with simple, thoroughly tested components. The system and application software execute in a deterministic way, which means there are also that no process driven interrupts. The system has also been designed to identify and cope with failures using extensive self-monitoring and fault handling.

 


Caption: Visulization of the six-unit Fuqing Nuclear Power Station in China (Source:CNNC)

 



Privacy Policy
We have updated our privacy policy. In the latest update it explains what cookies are and how we use them on our site. To learn more about cookies and their benefits, please view our privacy policy. Please be aware that parts of this site will not function correctly if you disable cookies. By continuing to use this site, you consent to our use of cookies in accordance with our privacy policy unless you have disabled them.