Poland’s Council of Ministers has adopted the first update in six years to the Polish Nuclear Power Programme (PPEJ – Program Polskiej Energetyki Jądrowej). This conforms that the first NPP is now scheduled to start up in 2036, three years later than previously planned, and the second in 2040, one year later than planned.

The delays were widely expected, as Poland is already behind the schedule set out in the previous PPEJ, adopted in 2020. However, the government says Poland is still on track for nuclear to be providing around 15-16% of electricity generation by 2040.

“This is not just a plan to develop new capacity, but also to build a strong Polish nuclear industry,” Energy Minister Miłosz Motyka said in a post on X. “We are building a nuclear sector that will drive the Polish economy and serve our security for decades to come.”

He reiterated that the revised programme outlines a collective plan to deliver up to 9 GWe of new nuclear capacity across the upcoming stations. He highlighted a progressively scaling target for local involvement, stating that subsequent nuclear units are designed to eventually reach up to a 70% share of participation from domestic Polish companies. He paired these figures with an emphasis that this update represents a deliberate plan to forge an entirely new, self-sustaining high-tech industrial sector within Poland rather than just purchasing foreign infrastructure.

Under the updated PPEJ, Poland plans to develop two NPPs with a combined capacity of around 6-9 GWe using large-scale Generation III+ reactors. The first plant, comprising three AP1000 units, is being built in partnership with an American consortium comprising Westinghouse and Bechtel in the municipality of Choczewo (Pomerania) on the Baltic coast. Preparatory work at the site is underway.

The European Commission last year approved Polish state aid for the project, which is set to receive PLN60.2bn ($15.5bn) in public support between 2025 and 2030. In March, project company Polskie Elektrownie Jądrowe (PEJ) applied to the State Atomic Energy Agency (PAA – Państwowa Agencja Atomistyki) for a construction permit submitting a 40,000-page safety justification. By law, the PAA has 24 months to review this documentation. First nuclear concrete is scheduled for 2028, with the three units due to start up in 2036, 2037 and 2038.

A second NPP is planned, with construction scheduled to begin in 2032 and the first unit expected to come online around 2040. The preferred sites for that plant are Bełchatów and Konin in central Poland and companies from the US, France and Canada are competing to supply the technology. A supplier decision is expected in 2027.

Given the global track record of the AP1000, Poland’s three-year delay before construction has begun fits into a predictable pattern. The project in Poland is being watched closely because previous AP1000 builds faced significant difficulties.

Units 3&4 at the Vogtle plant in Georgia, the first AP1000s built in the US, suffered from a seven-year delay and saw their budget more than double. The delays pushed the original designer, Westinghouse, into Chapter 11 bankruptcy in 2017. While China eventually got the world’s first AP1000s online at the Sanmen and Haiyang NPPs, these faced delays of 4-5 years due to design changes, supply chain bottlenecks, and component failures during testing.

To try to ensure the 40,000-page safety review now being considered by PAA does not compromise the project timeline, the government passed a major amendment to the Special Nuclear Act in August. This simplifies the administrative workflow, allowing PEJ to use early partial opinions from the PAA to begin preliminary foundational works on-site, ensuring that ground clearance can progress while the final safety licence is still being processed.

Moving the timeline to 2036 was largely forced by the realisation that securing environmental decisions and preparing the Baltic coastal site is taking longer than politicians initially projected. While key steps have been taken to clear these hurdles, the complex interplay between environmental regulations and site preparation continues to carry a risk of further delay.

Westinghouse and Bechtel argue that Poland will not repeat Vogtle’s mistakes because those were “First-Of-A-Kind” (FOAK) errors. The supply chain has now been established, the design is fully mature, and lessons from Georgia and China are supposedly integrated.

However, because Poland is building an entirely new nuclear industry from scratch without an existing specialised workforce, domestic supply chain, or mature nuclear regulator. A 2036 startup assumes flawless execution from this point forward.