Slovakia has taken full ownership of its new nuclear plant project after state-controlled company JAVYS (Jadrová a vyraďovacia spoločnosť) signed an agreement to buy out the remaining 49% stake in joint venture JESS (Jadrová energetická spoločnosť Slovenska) from the majority Czech state-owned utility ČEZ.
Slovakia and ČEZ established JESS in 2009, during the first government of current Slovak Prime Minister Robert Fico. Among other things, ČEZ was tasked with providing know-how. Fico’s current government has decided that the new NPP will be state-owned.
The final agreed purchase price was €189.4m ($212m). The valuation, initially prepared by global accounting firm EY, was later audited and verified by KPMG to resolve internal government disputes regarding the buyout cost. The purchase price had sparked a dispute between Fico and Slovakia’s Ministry of Economy, but the KPMG valuation confirmed the original valuation of ČEZ Group’s stake in JESS. The government subsequently transferred responsibility for preparing the construction of the new nuclear power plant from the Ministry of Economy to the government commissioner for nuclear energy development and the Government Office.
“When we established the joint venture almost 17 years ago, our aim was to prepare the project so that Slovakia could build a nuclear power plant at Jaslovské Bohunice. The Bohunice site is currently the best-prepared location for building a nuclear power plant anywhere in Europe,” said ČEZ Board Chairman & CEO Daniel Beneš after signing the agreement.
He said that preparations for the new plant had included approval of a feasibility study, the securing of capacity reservation certificates, a positive environmental impact assessment (EIA), a siting permit under the Atomic Act and the acquisition of land needed for the project. Proceedings for a zoning decision have also begun.
The buyout paves the way for Slovakia to build a new 1,200 MWe reactor at the existing Jaslovské Bohunice site, using existing infrastructure with an estimated project cost of at least €10.9bn targeted for completion by 2040.
Bratislava shut down two units of the older VVER-440 units at the plant in 2006 and 2008 as a condition for European Union membership. The site currently hosts two VVER-440 units commissioned in 1984 and 1985, operated by Slovakia’s largest electricity producer, Slovenské elektrárne (SE), part of Energetický a průmyslový holding (EPH).
According to earlier reports, the US Westinghouse is expected to become Bratislava’s main partner in building the new NPP at Jaslovské Bohunice.
South Korea’s KHNP was originally considered a strong contender after winning a major bid in the neighbouring Czech Republic. However, it pulled out of the project in face of intense legal pressure and a subsequent intellectual property (IP) settlement with Westinghouse
To salvage the Czech project, KHNP and its parent company KEPCO signed a restrictive global IP settlement with Westinghouse in January 2025, which severely crippled KHNP’s ability to compete elsewhere. The deal explicitly barred KHNP from entering new nuclear markets in EU member states (except its existing Czech contract), North America, the UK, Japan, and Ukraine.
For any reactor KHNP is allowed to export, it must pay Westinghouse $175m in licensing fees and purchase $650m worth of Westinghouse goods and services. This obliterated the profitability of South Korean reactor exports in Europe.
Although Slovakia signed early memorandums of cooperation with EDF, French options were ruled out for this specific unit because EDF did not offer a reactor that matches Slovakia’s targeted 1,200-MWe capacity output.
Rosatom is strictly excluded from competing due to geopolitical sanctions. PM Fico explicitly stated that further nuclear cooperation with Russia is politically impossible under current global conditions, despite the fact that Slovakia’s existing operational units rely on Russian VVER technology.