Poland’s nuclear project company Polskie Elektrownie Jądrowe (PEJ) has commissioned Westinghouse Electric Company to begin procuring long-lead items for unit 1 of Poland’s first NPP. This represents a shift from design and planning into the initial phase of physical project execution.

Long-lead items are highly engineered, massive components that require years to manufacture due to stringent quality standards and a limited global supply chain. The initial order covers six critical components of the nuclear island, including the reactor containment vessel and associated structural modules.

Ordering these components ahead of time prevents project delays while PEJ and the Westinghouse-Bechtel consortium finalise the remaining aspects of the Engineering, Procurement & Construction (EPC) agreement. A consensus was reached in late September on the main commercial terms of the upcoming EPC contract.

“Thanks to the agreement reached in September between PEJ and the Consortium on the main commercial terms of the EPC contract, we are now ready to take the next step, namely begin the process of ordering long-lead items, explained Wojciech Wrochna, Secretary of State at the Ministry of Energy and the Government Plenipotentiary for Strategic Energy Infrastructure. “We adopted this approach in order to give ourselves time for further detailed negotiations on the EPC contract, without the pressure that the lack of a long-lead item order would affect the project schedule. A sound contract that appropriately balances liability and establishes cooperation mechanisms for the construction phase is key to the project’s future success.”

The multi-billion-dollar project, situated at the Lubiatowo-Kopalino site in the Pomerania region on the Baltic coast will comprise three Westinghouse AP1000 reactors with a total generation capacity of roughly 3,750 MWe. General contractor Bechtel took control of the site coordinates in August to begin initial earthworks and site levelling, with first concrete currently scheduled for 2028.

Construction of each reactor is expected to take about seven years. This will be followed by approximately one year of testing and commissioning. The aim is for the first reactor to begin commercial operation in 2036, the second in 2037, and the third in 2038. This is three years later than originally planned.

“This is an extremely important moment for the entire project. Securing long-lead items is of direct significance for the construction schedule of Poland’s first nuclear power plant, said Minister of Energy Miłosz Motyka. We want energy from the first reactor to reach our power outlets in 2036. This is a strategic project by the Polish government that will meet our needs for decades to come, becoming one of the cornerstones of our country’s energy security.”

PEJ Management Board President Marek Woszczyk noted: “In nuclear projects, proper preparation and effective time management are crucial. We have already ordered the first long-lead items for which Bechtel is responsible, and we are now beginning this process for Westinghouse, which is responsible for the nuclear portion of the power plant in the broadest sense. In this way, we safeguard not only the project schedule but also its budget. The components we order account for a significant part of our costs, so starting the process well in advance allows us to better control our expenses in the coming years.”

The early procurement initiative also provides an entry point for certified domestic Polish suppliers to join the global nuclear supply chain under the international ASME NQA-1 safety standard. Woszczyk said ordering long-lead items “is a critical first step for Polish industry to furnish nuclear-grade components for the plant and maximise its participation in Poland and in future AP1000 projects in Europe”.

Procuring long-lead items for a Westinghouse AP1000 nuclear island requires an exclusive network of highly specialised global manufacturers. Because these massive components must withstand extreme nuclear pressures and meet stringent international safety standards, only a few companies globally possess the required heavy-forge and precision-engineering capabilities.

The primary companies likely to be contracted, or already confirmed, to supply these critical long-lead components for the Polish plant include:

  • Doosan Enerbility (South Korea): Doosan is historically Westinghouse’s primary partner for fabricating ultra-heavy nuclear island components. Doosan has some of the world’s largest forge presses and have previously manufactured the reactor pressure vessels (RPVs) and steam generator forgings for the AP1000 reactors built in the US (Vogtle) and China (Haiyang and Sanmen).
  • Sheffield Forgemasters (UK): Westinghouse signed an expanded supply chain agreement with this heavy engineering firm to supply cast and forged steel components. They have an established history of forging nuclear-grade steel components for the AP1000 supply chain.
  • Curtiss-Wright Corporation (US – specifically, the Electro-Mechanical Division facility in Cheswick, Pennsylvania): The AP1000 design uses specialised, high-reliability “canned-motor” reactor coolant pumps. Curtiss-Wright is the sole qualified supplier in the West capable of manufacturing these 187-tonne pumps, making them an indispensable long-lead contractor for this project.
  • Framatome (France): Framatome, a subsidiary of France’s state-backed energy giant EDF, was chosen to supply the steam circulation equipment and instrumentation for the Polish AP1000 project.
  • Jeumont Electric (France): The company provides key auxiliary electric motors and heavy-duty components within French and international nuclear island ecosystems.
  • Polish companies: Bechtel recently awarded a contract to this major engineering firm to construct two large-scale Module Assembly Buildings (MABs) directly at the Choczewo site. While the raw steel and advanced containment plates may originate from global suppliers, Polimex Mostostal will assemble these huge structural modules before they are lifted into place. Companies such as ZRE Katowice, Mostostal Warszawa, and APS Energia have spent years certifying under nuclear-grade codes to supply sub-components, electrical systems, and structural steel embedded within these long-lead modules.

The estimated manufacturing and delivery timeline for the long-lead items is between three and 5.5 years. Because heavy nuclear island components cannot be mass-produced and are built entirely to order, the timeline is tightly synchronised with Poland’s broader construction schedule. The procurement orders kicked off in October. Complex components such as the structural modules and the reactor containment vessel sections will take several years to forge, weld, and test at specialised international facilities.

Site delivery is targeted for 2030–2031. Components must arrive at the Pomeranian site sequentially. Groundwork and site levelling are already underway, but the long-lead items need to arrive after the site is fully excavated and before major structural concrete works peak. PEJ has scheduled the pouring of first concrete for the fourth quarter of 2028. Securing the items is intended to ensure that as soon as the concrete base is ready, the heavy reactor components are either already on-site or in the final stages of shipping. This strict timeline is designed to keep unit 1 on track for grid connection and commercial operation by 2036.

Once completed, these ultra-heavy components (some weighing more than 500–1,000 tonnes) will face a complex transport route. They will be shipped via heavy-lift marine vessels across the Baltic Sea. Since the final destination is the coastal Choczewo municipality, the components will probably be offloaded at a designated marine offloading facility (MOLF) built near the site or through major Polish ports before being moved over a short, heavy-haul land route to the Module Assembly Buildings.