Polish nuclear developer SGE (formerly known as Synthos Green Energy) and private power company ZE PAK have signed an agreement to establish a joint venture, PAK BWRX, to build and operate a major nuclear project in central Poland.

The joint venture aims to deploy six BWRX-300 small modular reactors (SMRs) designed by GE Vernova Hitachi Nuclear Energy (GVH), to supply a total capacity of 1,800 MWe. The Pątnów SMR project runs parallel to Poland’s large-scale nuclear ambitions, which include building three Westinghouse AP1000 units on the Baltic coast.

GVH acts as the core designer and technology provider for the BWRX-300 – a 300 MWe water-cooled, natural circulation SMR featuring passive safety systems. It leverages the design and licensing basis of GVH’s US Nuclear Regulatory Commission (NRC)-certified ESBWR boiling water reactor design and its existing, licensed GNF2 fuel design.

The reactors will be built at the site of the retiring Pątnów coal-fired power plant, located roughly 240 kilometres southwest of Warsaw. Repurposing this site preserves an essential hub for Poland’s national electricity grid. SGE, founded by Polish billionaire Michał Sołowow, holds the exclusive promotion rights for these SMRs in Poland and will maintain a majority stake in the new joint venture. ZE PAK is controlled by the prominent Solorz family.

This partnership addresses critical infrastructure challenges as Poland seeks to modernise its ageing energy mix. Poland faces a projected 5 GWe reliable capacity shortfall by 2032 due to coal plant retirements, while power demand is expected to surge by 40% over the next 14 years due to industrial growth, data centres, and EV infrastructure.

The rollout of the six SMRs at Pątnów operates on an incremental timeline, strictly tied to the decommissioning and site handover schedule of the existing infrastructure. The SGE-ZE PAK partnership will now embark on a five-year developmental roadmap which will include assessments and obtaining key regulatory and building licences.

The sale price of the property will be settled by the joint venture in instalments beginning in 2028. The land at Pątnów is systematically scheduled to be handed over to PAK BWRX, the special-purpose vehicle (SPV), by 2030 as coal-fired capacities face decommissioning.

The structure and financial governance of the SPV establish clear parameters for the joint venture between SGE and PAK SMR (a subsidiary of ZE PAK). SGE acts as the managing partner in the venture and holds the explicit right to appoint the majority of members to the SPV’s governing bodies (the Management Board and Supervisory Board). PAK SMR retains the right to appoint the remaining minority members.

The land designated for the six SMRs at Pątnów will be transferred to the SPV through a combination of an in-kind capital contribution and a direct sale. The base net price of the property is set at PLN300m ($76.6m). However, this price can be adjusted downwards by up to PLN50m, depending on the costs incurred to prepare the brownfield coal site for the nuclear infrastructure. Rather than a lump sum, the SPV will pay for the land in instalments from 2028 to 2030, culminating in the official site handover in 2030.

Once the site is formally cleared and transferred, physical site preparation and construction can start. By using a brownfield power station layout, the project significantly cuts down on overall grid-connection time. Pątnów is already one of the most critical energy distribution hubs in central Poland. The presence of high-voltage transmission lines minimises the need for building entirely new electrical infrastructure. The site possesses functional water access historically used for the coal facility’s cooling needs. This will be converted to support the BWRX-300.

“Pątnów… is one of the most strategically important locations in Poland’s energy system,” said SGE Founder Michał Sołowow. “The existing lignite-fired power plant will inevitably have to shut down, and without a reliable replacement, its closure could disrupt grid operations. Replacing coal-fired generation with nuclear power based on SMR technology will bring Poland’s energy system into the 21st century…. This project will make a significant contribution to Poland’s energy security and broader national security. Above all, it will strengthen the competitiveness of Polish industry and create new opportunities for economic growth.”

Piotr Żak, President of the Management Board of ZE PAK noted: “Building a nuclear power plant on the site of our former coal operations would be a model example of Poland’s energy transition. The energy and fuel crises of recent years have made one thing clear: Poland needs reliable, domestic sources of electricity. The six SMR reactors planned for the ZE PAK site can provide exactly that.”

The Pątnów project is the latest addition to SGE’s nuclear development portfolio in Poland, based on BWRX-300 technology developed through American, Polish, and Canadian cooperation. SGE is a co-investor and co-owner of the technology and holds the exclusive promotional and deployment rights for the BWRX-300 technology within Poland.

SGE operates on a repeatable, fleet-based deployment model designed to cut construction costs and speed up delivery timelines by leveraging uniform supply chains across multiple regions. Beyond the PAK BWRX joint venture, SGE has built a footprint in Poland through ORLEN Synthos Green Energy (OSGE) – a separate joint venture with state energy giant ORLEN targeting up to 26 SMRs across Poland.

SGE has submitted a proposal to build a 14-reactor fleet (4.2 GWe capacity) across three multi-unit sites in the UK. The project has been selected for the UK Department for Energy Security & Net Zero’s Advanced Nuclear Framework process. In addition, SGE is structuring SMR pipeline frameworks in Sweden, Bulgaria, Hungary, and Lithuania.

Construction of the world’s first BWRX-300 reactor is underway at Darlington in Ontario, Canada, where four units are planned. In the US, the Nuclear Regulatory Commission (NRC) has issued a construction permit to the Tennessee Valley Authority for the first BWRX-300 reactor at the Clinch River site. The technology has also been selected for projects being developed by SaskPower in Canada, Blue Energy in the United States, and Studsvik in Sweden.

In September, SGE, GE Vernova, Hitachi, and Samsung C&T signed a cooperation agreement in New York to support BWRX-300 deployment in Central and Eastern Europe and the UK. The partnership combines the technology, industrial capabilities, and construction expertise of leading global companies to support a common supply chain and fleet-scale reactor deployment across Europe. Also in September, at the Company conference in Warsaw, SGE announced that the investor group will commit a combined PLN500m to support the programme’s development in Poland and across Europe.