US multinational technology and cloud-computing company, Oracle, has committed to buying 125-250 MWe from NextEra’s Point Beach NPP in Wisconsin. This strategic power purchase agreement (PPA) will absorb roughly $300m in rising fuel costs, shielding more than 1m We Energies utility customers from heavy rate price rises.
We Energies sold Point Beach to NextEra Energy in 2007. However, the PPAs with the plant remained in place after the sale, with Unit 1’s contract running through 2030 and Unit 2’s through 2033. These long-term purchase contracts have been weighing on the company’s finances.
“Oracle is stepping up with a commitment that will directly benefit more than 1 million Wisconsin utility customers,” said Mahesh Thiagarajan, executive vice president, Oracle Cloud Infrastructure. “By absorbing approximately $300 million in rising energy costs, we are helping protect Wisconsin ratepayers while supporting the reliable, carbon-free power the state depends on. This is a meaningful investment in Wisconsin’s future—and in the communities we are proud to serve.”
The purchased power will supply Oracle’s data centre campus in Port Washington. If the plan is realised, approximately $300m in fuel costs borne by We Energies customers will shift to Oracle. Implementation requires approval from the state’s Public Service Commission (PSC) with official filings expected by the end of the year.
The energy acquired from the nuclear facility will be used to power Oracle’s new Project Lighthouse data centre campus in Port Washington, Wisconsin. This $15bn AI data centre initiative, co-developed with OpenAI and Vantage Data Centers, is projected to generate $11bn for the local economy and create thousands of jobs.
This move highlights an emerging tech-industry trend with AI companies securing direct, long-term deals with nuclear plants to feed their huge electrical footprints without triggering an energy cost crisis for local residents.
According to Oracle Vice President Julia Robin, the official proposal detailing the nuclear PPA is expected to be filed with Wisconsin state officials by the end of 2026. Once submitted, the PSC will conduct a formal, multi-month regulatory review of the agreement to assess how it structures ratepayer protections and handles the redistribution of the $300m in fuel costs.
While the Point Beach PPA is a voluntary cost-mitigation agreement, the physical campus cannot energise without a new high-voltage line connection, which faces an adjusted regulatory timeline.
In September, the American Transmission Company (ATC) refiled its high-voltage line application with the PSC, which had previously closed the initial 2025 case without ruling. ATC had introduced hundreds of late alterations to the route, leaving no time for the mandated environmental reviews before the original legal deadline. By refiling in late September, the statutory timeline for the state’s transmission review has officially reset.
Because the transmission infrastructure timeline has been pushed back, independent research firm Aterio projects that the initial timelines for Project Lighthouse face meaningful delays. The expected arrival of first grid power/partial power delivery is now December 2027, putting Oracle’s initial mid- 2027 target at risk.
The projected window for testing, building energisation, and commissioning before the data centre can carry customer workloads is now the first quarter of 2028. The full power supply delivery window, depending on whether the ongoing PSC transmission review encounters further extensions, is October 2028 to April 2029.