Novovoronezh 3 begins PLEX

30 May 2001


Novovoronezh 3 has been shut down in preparation for the start of work to extend its design life by up to 15 years. The existing operational period of the VVER-440 reactor ends next year, but the unit has been halted now in preparation for six months of work during which 21 technical projects will be carried out to improve safety systems.

The work is the start of plans that will extend the operating lifetimes of 12 first-generation reactors, including units 3 and 4 at Novovoronezh. The cost of modernising Novovoronezh 3 is estimated at about R600 million ($21 million).



Privacy Policy
We have updated our privacy policy. In the latest update it explains what cookies are and how we use them on our site. To learn more about cookies and their benefits, please view our privacy policy. Please be aware that parts of this site will not function correctly if you disable cookies. By continuing to use this site, you consent to our use of cookies in accordance with our privacy policy unless you have disabled them.