More delays announced for OL3

23 August 2021


Olkiluoto 3 turbine (Photo: TVO)Regular electricity production from the EPR plant at unit 3 of the Olkiluoto NPP (OL3) will be further postponed for three months due to extended turbine overhaul and inspection works, Finnish power company Teollisuuden Voima Oyj (TVO) said on 20 August, noting it had received additional information from the plant supplier Areva-Siemens consortium.

During the turbine inspection works, the plant supplier decided to extend the overhaul to all three low-pressure turbines in order to perform further inspections on them, TVO noted. According to information from the plant supplier, first criticality of the OL3 EPR reactor will take place in January 2022, first electricity production in February 2022, and the regular electricity production in June 2022.

 OL3 plant supplier consortium is constructing the plant unit under a fixed-price turnkey contract. The supplier consortium companies, AREVA GmbH, AREVA NP SAS and Siemens AG, have joint and several liability for the contractual obligations until the end of the guarantee period of the plant unit. 

The hot functional test phase is underway at OL3, a 1600MWe Generation III EPR. TVO said in July that after receiving the test results it had been decided to conduct some additional overhaul and inspection work for the turbine. The start of regular electricity production was then postponed until to March 2022. The project to build OL3, which began in 2005, is some ten years behind schedule and significantly over budget.


Photo: Olkiluoto 3 turbine (Photo: TVO)



Privacy Policy
We have updated our privacy policy. In the latest update it explains what cookies are and how we use them on our site. To learn more about cookies and their benefits, please view our privacy policy. Please be aware that parts of this site will not function correctly if you disable cookies. By continuing to use this site, you consent to our use of cookies in accordance with our privacy policy unless you have disabled them.