Kyushu to decommission Genkai 2

14 February 2019


Japan’s Kyushu Electric Power Company has announced plans to decommission Genkai 2, a 559MW pressurised water reactor in Saga Prefecture.

Genkai 2 started construction in June 1976 and entered commercial operation in March 1981. The unit was taken offline in January 2011 for a routine outage and has not resumed operation Post-Fukushima. Its operating licence expires in March 2021.

To extend the reactor’s operating life, Kyushu would need to submit a licence extension application to Japan's Nuclear Regulation Authority by 31 March 2020.

Kyushu said it had been considering applying for an extension, but in light of new regulatory safety standards and the lack of space at the site to construct facilities required it decided not to go ahead.

Over its lifetime Genkai 2 has generated 119.7TWh of electricity, operating at a load factor of 81%, and playing an important role in providing a stable power supply and in maintaining a low electricity price.

Genkai 1&2 will now be decommissioned with the “highest priority” on safety, Kyushu said. The utility also operates Genkai 3&4 and Sendai 1&2.



Privacy Policy
We have updated our privacy policy. In the latest update it explains what cookies are and how we use them on our site. To learn more about cookies and their benefits, please view our privacy policy. Please be aware that parts of this site will not function correctly if you disable cookies. By continuing to use this site, you consent to our use of cookies in accordance with our privacy policy unless you have disabled them.