The UK Office for Nuclear Regulation (ONR) on 7 September served an Improvement Notice on EDF Energy Nuclear Generation Ltd (EDF Energy) for shortfalls in safety procedures at Heysham 2 Power Station in Lancashire.

The notice was served after some of the equipment which is used to measure reactor power was incorrectly configured during the reactor’s restart process following a planned outage in April 2020.

Operators quickly detected the error during the start-up process at very low power, and the restart was safely aborted. A range of other safety barriers remained in place at the time of the incident, including other equipment to independently measure reactor power, and the safety of workers and the public was not compromised.

EDF Energy promptly reported the event and ONR was satisfied that appropriate measures had been taken before the reactor was allowed to restart. The circumstances have subsequently been investigated by ONR, as the independent regulator, and an Improvement Notice served to prevent a recurrence. EDF Energy must comply with the notice by 30 April 2021.

 



Privacy Policy
We have updated our privacy policy. In the latest update it explains what cookies are and how we use them on our site. To learn more about cookies and their benefits, please view our privacy policy. Please be aware that parts of this site will not function correctly if you disable cookies. By continuing to use this site, you consent to our use of cookies in accordance with our privacy policy unless you have disabled them.