Delays reported for Finland’s Hanhikivi NPP

30 August 2018


Finnish company Fennovoima, which is building a Russia-supplied 1,200MWe VVER pressurised water reactor at Hanhikivi, aims to receive a construction licence in 2019 and to begin construction in 2020, a spokeswoman told NucNet in an email on 29 August. Tiina Rytky, the company’s digital communications manager, was responding to unconfirmed reports in Russian media that the project is behind schedule. “We know it is a very challenging target, since a lot of the design material is still not delivered to the safety authority Stuk,” she said. “We have asked for an update of the project timetable from our plant supplier and we are expecting it at the end of this year.”

Fennovoima will use “all the time needed for designing the power plant”, she added. “We prefer to take time now than at the point when we are already on the construction site with thousands of workers.” According to Fennovoima’s website, the total investment cost for Hanhikivi-1 will be between €6.5 and €7bn, which includes initial plant costs, financing and waste management. This estimate has remained the same since spring 2014, when the original investment decision was made, Fennovoima said.

The Hanhikivi project is owned by Fennovoima. RAOS Voima Oy, the Finnish subsidiary set up in 2014 by Russian state nuclear corporation Rosatom, has a 34% stake in Fennovoima. Russia's Titan-2 is the main contractor for the project. Fennovoima submitted the construction licence application in the summer of 2015.

In March 2018 Fennovoima said it faced challenges in 2017 delivering design documentation to the regulator, but remained on track to receive the construction permit in 2019. In its corporate responsibility report for 2017, Fennovoima said taking Finnish requirements and legislation into account in the design work had taken more time than anticipated for plant supplier RAOS Project Oy, which is part of the Rosatom Group.

The reference plant for Hanhikivi-1 is Leningrad II in Sosnovy Bor where two VVER V-491 units are under construction. Comprehensive final testing at unit 1 of Leningrad was completed earlier in August. 



Privacy Policy
We have updated our privacy policy. In the latest update it explains what cookies are and how we use them on our site. To learn more about cookies and their benefits, please view our privacy policy. Please be aware that parts of this site will not function correctly if you disable cookies. By continuing to use this site, you consent to our use of cookies in accordance with our privacy policy unless you have disabled them.