Compromise over closure of Chernobyl

8 January 1999


Chernobyl 3 was closed as planned on 15 December for preventive maintenance. Sergei Sharshun, shift superintendent, said there would be a routine check of safety systems; welded joints would be inspected and any defects repaired in the emergency reactor cooling system. The unit would be closed for two months.

The unit was originally scheduled for the outage on 1 December to repair and upgrade safety equipment, using $118 million from the EBRD. However, shutdown was postponed in the face of severe energy shortages, pending restart of a unit at the Zaporozhye plant.

The utility, Energoatom, wanted the unit to remain online into 1999 because of grid supply problems, but the regulator insisted on the planned outage taking place in early December.



Privacy Policy
We have updated our privacy policy. In the latest update it explains what cookies are and how we use them on our site. To learn more about cookies and their benefits, please view our privacy policy. Please be aware that parts of this site will not function correctly if you disable cookies. By continuing to use this site, you consent to our use of cookies in accordance with our privacy policy unless you have disabled them.