US start-up The Nuclear Company, has proposed plans for “Prosperity One”, a massive 6.6 GWe commercial nuclear power campus constructed along the Ohio River located in Lewis County, Kentucky. This would be the largest nuclear power campus in the US and Kentucky’s first-ever commercial nuclear power project.

The campus is designed to accommodate up to six Westinghouse AP1000 nuclear reactors. It would be constructed at Carrs Bottom along the Ohio River in eastern Kentucky (about 92 miles northeast of Lexington). The development team already controls or holds purchase options on more than 4,200 acres of land.

The 6.6 GWe capacity is enough to power more than the average electricity consumption of every home in Kentucky. The Nuclear Company is partnering with local community leaders, landowners, and Trace Creek Construction founder Sam Howard to advance the project.

Earlier this month, Lewis County leaders voted overwhelmingly to submit a filing to the Kentucky Nuclear Energy Development Authority to pursue a “nuclear ready community” status. The Nuclear Company is preparing detailed site characterisations, environmental assessments, and transmission planning. They will engage the Nuclear Regulatory Commission (NRC) for safety and licensing approvals. The company aims to secure necessary federal approvals to officially break ground and begin construction in 2028.

“For generations, communities along the Ohio River have formed America’s industrial backbone,” said Joe Klecha, Chief Nuclear Officer for The Nuclear Company. “We are proud to partner with the community to apply our team’s collective experience to deliver lasting jobs, a stronger tax base, and reliable power for Kentucky.”

To advance Prosperity One from a proposal to an active construction site, The Nuclear Company must navigate a rigorous, multi-year regulatory process overseen primarily by the U.S. Nuclear Regulatory Commission (NRC).

Because the project relies on Westinghouse AP1000 reactors, a design that has already received standard design certification from the NRC, the regulatory path is significantly streamlined compared to untested reactor technologies. However, securing a licence for a new location requires several critical steps.

Before formally submitting a licensing application, the developer must conduct extensive localised technical studies. These studies are necessary to prove the Carrs Bottom location along the Ohio River is safe and suitable. This will include:

  • Geotechnical & seismic investigations – testing soil and bedrock stability to ensure the ground can support up to six massive reactor facilities.
  • Environmental assessments – measuring impacts on local water resources (the Ohio River), local wildlife, and surrounding ecosystems.
  • Transmission interconnection planning – working with regional grid operators to ensure the infrastructure can safely handle injecting 6.6 GWe of new electricity into the power grid.

The Nuclear Company will pursue one of two established federal licensing structures through the NRC. Under NRC’s “Part 52” framework, the developer can apply for a Combined Licence Application (COLA), a single licence that covers both construction and conditional authority to operate the plant. Because the AP1000 design is pre-approved, the NRC’s review focuses heavily on site-specific safety, environmental impacts, and emergency preparedness. Alternatively, the company could resolve site-suitability and environmental questions early by applying for an Early Site Permit before finalising the specific construction details.

Once the application is officially docketed, the NRC begins a exhaustive evaluation process that typically takes several years. The Safety Evaluation Report (SER) requires NRC staff to analyse structural engineering, security protocols, aircraft impact resistance, and cyber security layouts. For Emergency Preparedness, the developer must coordinate with local Lewis County, state, and federal emergency management agencies to establish robust evacuation and safety boundaries.

Nuclear licensing is legally required to include opportunities for public participation. The NRC will hold formal public comment periods and local hearings in Kentucky, allowing residents, environmental groups, and stakeholders to voice support or raise concerns regarding radioactive waste, safety, and water usage.

While federal approval dictates safety and operations, state-level approval manages the commercial footprint.

  • Kentucky Nuclear Energy Development Authority (KNEDA) -Lewis County is currently pursuing full “Nuclear Energy Ready Community” certification to demonstrate local infrastructural readiness.
  • Certificate of Public Convenience and Necessity (CPCN) – The project will require approvals from state utility regulators regarding who will purchase the electricity, the cost of transmission upgrades, and consumer rate impacts.

The Nuclear Company’s aggressive goal to break ground by 2028 means they will need to initiate formal pre-application engagements with the NRC in the near future to meet their timeline. While the timeline is not impossible, nuclear experts generally view a two-year window from project announcement to a formal NRC construction permit as incredibly compressed.

Rapid nuclear approvals typically happen following years of “pre-application engagement” with regulators. The Nuclear Company has just announced Prosperity One and is only now beginning site characterization, geotechnical engineering, and environmental baseline reviews.

Even if NRC moves at record speed, securing a Transmission Interconnection Agreement for 6.6 GWe is a major hurdle. Grid operators currently face massive backlogs, with typical queues for large-scale energy injection taking 3-5 years just for study approvals.

As a wave of tech-backed nuclear start-ups (such as Oklo and TerraPower) simultaneously flood NRC with applications, the regulatory body faces severe staffing constraints. If multiple gigawatt-scale applications land at once, NRC’s target timelines are highly likely to stretch.

Realistically, the 2028 timeline acts more as an aggressive target to align stakeholders, build investor momentum, and push the regulatory envelope. Given that no construction can begin until both federal and state regulators fully sign off, a more realistic expectation based on historical precedent would see actual heavy construction breaking ground closer to 2030 or 2031.