In the long-running legal battle over the cancelled €7bn ($7.85bn) Hanhikivi-1 nuclear power project in Finland, both Rosatom and Finnish utility Fennovoima claimed partial victories following a ruling by the International Chamber of Commerce (ICC) tribunal. The conflicting interpretations came after the panel validated specific, opposing legal arguments from both companies.

The ICC tribunal upheld Russia’s counterclaim, ruling that Fennovoima unlawfully terminated the engineering, procurement, and construction (EPC) contract in May 2022. Rosatom highlighted that the panel found the project was making satisfactory progress at the time of cancellation.

Despite the ruling on the contract termination, the tribunal recognised that Fennovoima was entitled to recover its advance payments and interest, which exceeded €1bn. However, the tribunal offset the financial claims from both sides, resulting in a net order for Rosatom’s subsidiaries to pay €606m plus interest to Fennovoima. While Fennovoima secured a substantial financial payout, Rosatom maintains a critical legal advantage regarding the illegality of the contract termination as proceedings continue.

The Hanhikivi-1 nuclear power project was for the construction of a 1,200 MWe NPP on the Hanhikivi peninsula in Pyhäjoki, northern Finland. The primary goals were to strengthen Finland’s energy independence and significantly reduce greenhouse gas emissions by supplying roughly 10% of the country’s electricity.

The project took shape in December 2013 when the Finnish consortium Fennovoima signed a fixed-price engineering, procurement & construction (EPC) contract with Rusatom Overseas (a subsidiary of Rosatom). Fennovoima was structured as a joint venture where Finnish stakeholders (including major corporations like Fortum, Outokumpu, and SSAB, alongside local energy companies) held 66% of the shares. The remaining 34% was owned by RAOS Voima Oy, a Finnish subsidiary set up by Rosatom.

The plant was designed to use Russia’s Generation III+ AES-2006 VVER pressurised water reactor. By the time the project halted, Fennovoima had begun constructing production-assembly facilities at the site and was in the process of securing its final construction licence from Finland’s Radiation and Nuclear Safety Authority (STUK – Säteilyturvakeskus).

In May 2022, Fennovoima terminated the contract with RAOS and subsequently withdrew its construction licence application. The company cited two arguments for the abrupt cancellation. Fennovoima stated that the primary legal basis for the termination was the Russian supplier’s inability to deliver the project. The venture had allegedly faced logjams in the design, licensing, and preparatory phases, pushing the estimated start date past its initial target.

While the delays served as the formal contractual breach, the immediate catalyst was the start of the conflict in Ukraine in February 2022. Fennovoima explicitly highlighted that the war exacerbated existing political risks to an untenable level, making it impossible to complete a critical national infrastructure project in partnership with a Russian state-owned enterprise in face of international sanctions.

Rosatom fiercely rejected these reasons, maintaining that the project was making sufficient progress toward licensing at the time, a point the ICC tribunal later validated as part of its split ruling. The ICC ruling hinges on the exact wording of the contract breach and the verified timeline of the construction process up to May 2022. The tribunal validated Rosatom’s position regarding the day-to-day progress of the build.

The tribunal recognised that at the exact time of the contract termination, the project was still actively progressing. Rosatom’s subsidiaries were deemed to be making demonstrable progress toward securing the vital final construction licence from STUK.

Because the panel determined the project was moving forward reasonably at that time, it ruled that Fennovoima had no contractual right to unilaterally terminate the EPC contract and using “inability to deliver” as a justification was legally invalid.

This would typically mean Fennovoima owed immense damages to Rosatom. However, the tribunal balanced this by recognising Fennovoima’s right to recoup its capital, creating the dual outcome. Claims were offset, resulting in the net €606m order against Rosatom.

For Rosatom, the validation of their project timeline is a long-term defensive shield. Rosatom Director General Alexey Likhachev explicitly noted that this victory is “important, but not final”. Rosatom has already initiated separate legal channels and lawsuits. They intend to leverage the tribunal’s finding that they were acting as a compliant, progressing supplier to contest further financial penalties and seek damages in other upcoming court venues. “At the same time, I would like to add that if we had continued to jointly implement the project, Finland would have received the latest nuclear power plant, and with it inexpensive and green electricity,” Likhachev noted.