South Korea’s Hyundai Engineering & Construction (Hyundai E&C) has signed a contract with Westinghouse to conduct basic design studies for two large nuclear plants in the Netherlands. Hyundai E&C will act as a core partner to US-based Westinghouse, carrying out Front-End Engineering Design (FEED 1) studies.
In August Nuclear Energy Organisation of the Netherlands (NEO NL) awarded parallel FEED 1 contracts to both EDF and Westinghouse. This dual-track approach serves as a competitive evaluation process to determine which technology will ultimately be chosen to build two new Generation III+ nuclear reactors.
Hyundai E&C is tasked with critical early-stage responsibilities, including technical feasibility reviews, assessing candidate construction sites, drafting master plans, establishing localisation strategies, and managing compliance with local regulations for two AP1000 plants.
The first phase of the design study (FEED 1a) is site-independent, allowing the engineering work to progress over an estimated 12-18 months while the Dutch government finalises geographic site selections.
Hyundai E&C has been building on its partnership with Westinghouse. Ahead of this contract, the two companies jointly held a Dutch supplier symposium in June, meeting with the local government, industry officials and nuclear companies to build a cooperation network and strengthen the supply chain base. The two have maintained a partnership across global nuclear projects and plan to combine their technology and project capabilities during the FEED work to strengthen the basis for taking part in later phases.
“Through this participation in FEED 1, we expect to contribute to the successful execution of the new nuclear project in the Netherlands and to establish ourselves as a competitive project partner in the subsequent phases as well,” a Hyundai E&C official said. “Based on the design and construction capabilities we have accumulated in the large reactor field, we will raise the quality of the project and continue to expand new business opportunities in the European nuclear market.”
This contract marks a significant milestone in Hyundai E&C’s strategy to anchor itself within Europe’s ongoing energy transition. The company’s active nuclear projects across the continent now include:
- Bulgaria – designing the Kozloduy large-scale nuclear power plant.
- Slovenia – conducting a Technical Feasibility Study (TFS) for a new nuclear power facility.
- Finland – executing an Early Works Agreement (EWA) alongside state-owned energy company Fortum.
- The Netherlands – the new FEED 1 basic design contract, follows a March Molten Salt Reactor (MSR) technology partnership with Dutch firm Thorizon.
By entering the initial design phases, Hyundai E&C intends to build early familiarity with regional regulations and site parameters, positioning itself as the preferred contractor for follow-on construction phases, assuming Westinghouse is selected.
France’s state-owned energy company EDF, is pitching its EPR (European Pressurized Reactor) design for the Dutch roadmap. NEO NL is running identical, parallel timelines for both EDF and Westinghouse after South Korea’s KHNP withdrew its APR1400 from the process in early 2025 after facing legal action from Westinghouse that effectively banned it from competing in the European market.
Both EDF and Westinghouse are conducting a 12-18-month site-independent study, evaluating how their respective systems comply with Dutch legislation, building codes, local safety guidelines, and grid synchronisation. Once the Dutch Cabinet announces its preferred site decision (with Borssele, Terneuzen, and Eemshaven under consideration), both companies will shift their studies to evaluate site-specific geology and local environmental impacts.
A previous feasibility review by the Dutch Authority for Nuclear Safety and Radiation Protection (ANVS – Autoriteit Nuclaire Veiligheid en Stralingsbescherming) highlighted distinct regulatory characteristics for both designs.
The EPR aligns seamlessly with European safety norms and leverages established EU regulatory framework experience. The design is highly robust but complex, which the regulator noted could lead to intricate local permitting processes. The AP1000 is a highly standardised modular design with a history of passive safety systems. It relies primarily on US standards, meaning it requires extensive documentation rewriting to clear Dutch legal frameworks.
To strengthen its bid, EDF has integrated local Dutch engineering and construction firms into its value chain. EDF has signed cooperation agreements with key Dutch industrial companies including Mammoet, DEME Offshore NL, and Royal HaskoningDHV. These partnerships aim to develop heavy-lifting methodologies and modular logistics tailored specifically to accelerate construction timelines in the Netherlands.
The results of these parallel FEED studies will serve as the primary data used by the Dutch government to select its final technology supplier.
Currently the Netherlands operates a single unit 485 MWe pressurised water reactor at the Borssele NPP, that has been in operation since 1973. It accounts for about 3% of total electricity generation. The plant had previously received approval to extend the operational period to 2033 and is now expecting to extend operation until 2054.