Unit 7 of the Tianwan Nuclear Power Plant in Lianyungang, East China’s Jiangsu Province has been connected to the grid. The ceremony marking the event was attended via video-link by Chinese President Xi Jinping, via video link from Beijing and Russian President Vladimir Putin.
Grid connection takes place once the reactor achieves approximately 25% of the nominal power. This will be followed by a long stage of gradual increase in power to nominal value as part of the pilot operation stage of the new unit after which its commercial operation and two-year warranty operation will begin.
In 2018, Russia and China signed four agreements, including for the construction of two VVER-1200 reactors for Tianwan units 7&8. Construction of unit 7 began in May 2021, and unit 8 in February 2022. Tianwan 7 is scheduled to be commissioned later this year and Tianwan 8 in 2027. Tianwan 1-4, with VVER-1000 reactors, commissioned between 2007 and 2018, are already in operation. Units 5&6 with Chinese ACPR-1000s were commissioned in 2020 and 2021.
Tianwan 7 will be the first Generation III+ VVER-1200 to begin operation in China. It represents an evolutionary step up from the older VVER-1000 models used in units 1–4. The VVER-1200 features double the expected operational lifespan (60 years). It also includes a two-thirds slower refuelling cadence and advanced passive safety systems. Once units 7&8 reach full capacity, they will collectively generate 18.8 TWh of electricity annually.
With all eight units in operation, the total capacity of the station will be 9,138 MWe, making it the world’s largest nuclear station by installed capacity. It is expected to reduce carbon dioxide emissions by 57.4m tonnes a year.
The Tianwan NPP is also the basis for China’s first industrial nuclear steam supply project, Heqi No1, which uses secondary-circuit steam from Tianwan 3&4 to supply industrial steam through an independent heat-exchange system to the Xuwei petrochemical industrial base about 23 kilometres away.