Unit 2 of Slovakia’s Mochovce NPP has been synchronised and connected to Slovakia’s national grid for the first time. The newly completed 471MWe VVER-440 reactor, operated by Slovenské Elektrárne (SE) has begun supplying low-carbon electricity to the Slovak transmission system.

“For the first time in its history, Mochovce Unit 4 is supplying electricity to Slovakia’s power system,” said SE Chairman & CEO. Branislav Strýček. “This is a moment generations of people who prepared, built and commissioned this project have been waiting for. Today, we are seeing the result of their work in the form of a new low-carbon source of electricity for Slovakia.”

The connection took place while the reactor was running at 20% power capacity. Only the first of the unit’s two turbine generators was initially aligned and synchronised to begin delivering electricity. Once it achieves full operational status, unit 4 will generate approximately 3.5 TWh a year – enough to cover roughly 13% of Slovakia’s overall electricity consumption.

The successful synchronisation followed a minor adjustment, having been delayed by just a few days from its original 13 October schedule to re-verify technical safety assessments.

This first synchronisation does not mark the conclusion of start-up activities. In accordance with oversight from the Nuclear Regulatory Authority, specialists will carry out the following trial milestones:

  • Align and synchronise the unit’s second turbine generator;
  • Execute mandatory safety, mechanical, and thermal checks at progressively higher power stages;
  • Complete a final, uninterrupted 144-hour trial run at 100% power; and
  • Transition into full commercial operations, which utility operators expect to reach by the end of 2026.

Slovakia is already highly reliant on nuclear energy, operating five other nuclear units (three at Mochovce and two at Jaslovské Bohunice) that handle over 60% of domestic power generation. Mochovce NPP comprises four VVER-440 units. Units 1&2 began operation in 1998 and 1999 and unit 3 began commercial operation in October 2023. Units 3&4 with a design life of some 60 years, will supply some 26% of Slovakia’s total electricity consumption.

Construction of units 3&4 began in 1986 but was suspended in 1992 and resumed only after a lengthy hiatus in 2008. SE puts the value of the entire project at approximately €6.7bn ($7.5bn), up from an estimated €2.8bn in 2008. With the addition of Mochovce 4, Slovakia will have six power reactors in operation. Slovakia also has two VVER-440 units operating at the Jaslovské Bohunice. With all six units in operation, nuclear power should cover approximately 77.5 % of domestic electricity consumption.