Google and Constellation Energy have reached a multi-billion-dollar power agreement to fuel Google’s expanding artificial intelligence (AI) data centres. The agreement is split into two primary commercial mechanisms across the PJM grid that serves 13 US states.
Under the 20-year power purchase agreement (PPA) Google is funding $4.3bn in equipment and technology upgrades across 11 existing Constellation nuclear units in Illinois, Pennsylvania, and New Jersey to bring 890 MWE of new nuclear capacity, with the first additional power scheduled to hit the grid in 2028. The agreement helps sustain roughly 4,400 existing jobs, creates approximately 7,200 new construction jobs during the building period.
In addition to expanding nuclear generation, the companies entered into a 15-year energy supply agreement for an additional 2,700 MWe for Google from PJM’s fleet. The financial structure ensures that Constellation’s operating generation assets continue to deliver energy and capacity to the PJM market not directly to Google facilities. This capacity is not tied to a single generation source but provides vital financial and revenue certainty to keep Constellation’s broad energy infrastructure economically viable. The arrangement is similar to that agreed earlier between Vistra and Meta (see related story) and follows similar reactor-uprate and restart agreements by peers such as Microsoft and Amazon.
As part of the package, the companies also entered a five-year technology alliance. Constellation will deploy Google Cloud and Gemini Enterprise to optimise grid operations. They plan to use AI for:
- Speed to power: streamlining site selection, permitting, and power flow modelling for faster infrastructure deployment;
- Asset monitoring: anticipating maintenance windows to keep generation running at peak capacity; and
- Cybersecurity: securing critical operational technology networks that connect directly to the bulk electric system.
“We’re committed to meeting our growth responsibly by actively investing in clean, reliable power that brings new capacity to our nation’s grids,” said Amanda Peterson Corio, Global Head Of Energy & Power at Google. “Our agreement with Constellation to fund nuclear reactor uprates will strengthen the PJM grid, which serves 67 million people, all while protecting energy affordability and supporting local union jobs.”
Joe Dominguez, Chairman, President & CEO of Constellation, noted: “Preserving and expanding the output of the existing nuclear fleet and developing new clean generation is critical to meeting our nation’s growing energy needs while keeping costs affordable for homes and businesses. This long-term clean energy collaboration with Google can serve as a model for how technology companies and the energy industry can work together to responsibly develop the digital economy and invest in our nation’s energy infrastructure in a way that delivers grid-wide benefits for all, funded by private entities.”
The agreement is strategically designed to navigate the PJM Interconnection grid’s upcoming Bring Your Own New Capacity (BYONC) framework, which encourages massive energy consumers to bring new capacity online rather than straining residential resources.
This framework, formally proposed by the PJM Interconnection grid operator in August, is a blunt regulatory response to the data centre boom straining the US power grid. PJM has filed BYONC framework with federal regulators to shield everyday consumers from the skyrocketing costs and reliability risks driven by artificial intelligence workloads.
The framework applies to New Large Loads, which are defined as any single facility (like a data centre campus) entering service after 1 June 2027, that demands a peak of 50 MWe or more. PJM’s rule gives these tech giants a direct choice: Fund and secure your own brand-new power generation off-grid or via bilateral contracts, or be the first to get turned off when grid stability is threatened.
Historically, when a power grid experiences a severe emergency (like a extreme heatwave or winter storm), grid operators trigger rolling blackouts that affect residential neighbourhoods and critical infrastructure equally.
Under the new Interim Resource Adequacy Service (IRAS) rules:
- Uncovered data centres will face mandatory remote power curtailment before the grid touches traditional consumers, local businesses, or homes;
- Effectively, data centres must rely heavily on their own onsite backup generators or temporarily shut down non-essential compute cycles during a grid crisis.
The decision is a response to the AI explosion and economic equity. PJM projects data centre demand alone will grow by a staggering 30 GWe by 2030, accounting for some 94% of all projected load growth across its 13 states. This load growth contributed to an 11-fold surge in PJM’s capacity market prices, tacking billions on to the collective cost of running the market. This BYONC framework aligns with the federal Ratepayer Protection Pledge, intended to ensure everyday residential electricity bills do not skyrocket to subsidise the massive infrastructure needed to power AI.