The fifth meeting of the Joint Coordinating Committee, attended by representatives of Armenia, Rosatom and its subsidiaries, took place in Yerevan as part of the programme for a second extension of the operating life of unit 2 of the Armenian NPP (ANPP). Participants reviewed the results of work carried out between 2024 and 2026.

The Russian delegation was headed by Rosatom First Deputy Director General Kirill Komarov, and the Armenian delegation by Deputy Minister of Territorial Administration & Infrastructure Narek Apitonyan. The meeting was also attended by Russian nuclear utility Rosenergoatom’s Deputy Director General responsible for Business Development, Nikita Konstantinov; Chairman of Armenia’s Committee for Nuclear Safety Regulation, Khachatur Khachikyan; the Head of Rusatom Service, Evgeny Salkov; and the Director of ANPP, Movses Vardanyan.

Buildings and structures covering a total area of 15,890 square metres were inspected. Documents were developed and agreed upon confirming the safe operation of the reactor plant until 2031. As part of the project, a detailed inspection of equipment, restoration annealing of the reactor vessel, and updating of safety systems and automated control systems are being carried out.

An action implementation plan for 2027–2030 was agreed and a protocol was signed. “Rosatom has completed a significant amount of work to improve the safety and reliability of the station, confirming that the reactor can operate safely until 2031,” said Salkov. “A set of works has already been planned for the coming year to improve the key systems of the Armenian NPP in order to ensure its further effective operation, until 2036.”

The ANPP was built in the 1970s with two Soviet-supplied VVER-440-V230 units but was closed following a devastating earthquake in 1988. However, unit 2 was recommissioned with Russian help in 1995 following severe energy shortages. The plant meets roughly 30% of Armenia’s domestic electricity demand. In March 2014, the Armenian government decided to extend the plant’s service life to 2026.

Most of the overhaul (until 2019) was funded by an interstate loan from Russia. In December 2024, following a meeting of the Armenian-Russian intergovernmental commission it was decided to extend the life of the plant until 2036. The Armenian government allocated $65m for the implementation of the programme, which is being undertaken by Rusatom Service. To execute core modernisations the plant was taken completely offline for a major 153-day maintenance window starting in April. Armenian technicians and Rosatom specialists completed some 20 critical reliability and safety measures, safely reconnecting the unit to the grid on 1 September.