Constellation Energy and Amazon have announced a 20-year power purchase agreement (PPA) agreement to support the continued investment in and expansion of the Calvert Cliffs Clean Energy Center in Maryland.

The Calvert Cliffs NPP is located on the western shore of the Chesapeake Bay near Lusby in Calvert County, Maryland. It comprises two Combustion Engineering 850 MWe pressurised water reactors and generates approximately 40% of Maryland’s total power and a significant majority (around 87%) of the state’s clean energy.

The agreement will enable more than $3bn in Maryland infrastructure investment, including state-of-the-art improvements across the entire plant and approximately 190 MWe in total of new generating capacity coming online between 2030 and 2032.

This deal represents a major pivot after Amazon scrapped earlier plans to build a data centre campus directly next to the plant in face of local opposition and political shifts in Maryland. In a recent primary election, voters ousted all three county commission members who had opposed a data centre moratorium.

Constellation is still willing to consider placing a data centre or another large customer at Calvert Cliffs, but as of now, “nothing is in the works”, said David Dardis, Constellation’s Senior Executive Vice President and chief external affairs and growth officer, in an interview with Maryland Matters. “We’re open to considering those sorts of arrangements, but we would only do so in partnership with Calvert County and other important stakeholders.”

Under the new arrangement, Amazon will purchase 690 MWe of power overall. Rather than being fed directly into isolated data centres, all electricity generated at Calvert Cliffs will continue flowing straight into the regional PJM Interconnection grid to strengthen the local power system.

The long-term revenue certainty allows Constellation to pursue a 20-year operational licence renewal for the facility (the current reactor licences run to 2034 and 2036), while exploring the future deployment of next-generation technologies such as small modular reactors (SMRs).

The deal represents a major pivot in how Amazon secures the massive amounts of continuous, carbon-free electricity needed to run artificial intelligence infrastructure. It shifts from a “behind-the-meter” direct hookup to a “front-of-the-meter” grid strategy. It serves as a blueprint for how tech companies can secure nuclear capacity without angering communities or drawing regulatory fire for hoarding grid resources.

By committing to buy 690 MWe from Constellation long-term, Amazon stabilises its utility exposure across the highly contested 13-state PJM regional power market. This helps to insulate Amazon Web Services (AWS) from surging electricity prices driven by the sudden explosion of regional data centre development.

This is Amazon’s first-ever agreement to fund a nuclear uprate project. It adds to Amazon’s expanding nuclear footprint, which includes a power deal with Talen Energy at the Susquehanna NPP in Pennsylvania and over $500m invested in SMR development in Washington state.

The Calvert Cliffs Clean Energy Center currently yields around 1,790 MWe. The planned state-of-the-art upgrades will boost the facility’s baseline capacity to 1,980 MWe – an expansion equivalent to all utility-scale wind and solar generation currently operating in Maryland.

To unlock the extra 190 MWe, Constellation will implement major mechanical and thermal modifications. This includes refining reactor equipment, optimising core fuel management, upgrading high-pressure turbines, and modifying instrumentation to handle higher steam flow and heat generation safely and efficiently.

The multi-year infrastructure overhaul will take place in phases, with the new capacity projected to come online between 2030 and 2032. Because Amazon will not siphon this power directly, the newly generated electricity will go straight into the local regional grid, providing enough baseline power to support up to 1.5m local homes while fulfilling Amazon’s contractual energy offsets.

“This agreement demonstrates how private investment can strengthen critical energy infrastructure,” said Constellation Chairman, President & CEO Joe Dominguez. “Amazon’s commitment supports the long-term operation of Calvert Cliffs for generations to come and creates a strong foundation for future investment in both the facility and in advanced nuclear technologies.”

Kerry Person, Vice President of AWS Global Operations & Data Center Delivery, noted: “Amazon is committed to investing in carbon-free energy to strengthen the grid and benefit the communities where we operate. This long-term agreement with Constellation sustains the continued operation and expansion of Maryland’s largest source of carbon-free energy, supports hundreds of jobs, and brings significant new generation to the regional grid.”

PPA deals are not new to Constellation, which plans to reopen the Three-Mile Island NPP (renamed the Crane Clean Energy Center) in Pennsylvania next year, under a 2024 20-year agreement with Microsoft. In June 2025, Constellation also signed a 20-year PPA with Meta for the Clinton Clean Energy Center in Illinois, which is expected to support its relicensing and add an additional 30 MWe to the plant.

Earlier this year, Constellation signed a multi-contract deal with Walmart to supply 176 MW over two staggered 15-year terms starting in 2029 and 2030. The baseline electricity will be drawn from the Dresden Clean Energy Center in Illinois to power new distribution infrastructure.