Rosatom has completed the vital hydraulic tests of the primary circuit systems and equipment at unit 1 of the Akkuyu NPP under construction in Türkiye. This confirms the leak-tightness of the primary circuit and serves as the pre-start-up inspection required before moving to hot functional testing.
The pressure within the primary circuit – which includes the reactor, main circulation pipeline, main circulation pumps, steam generators, and the pressuriser – was raised to 24.5 MPa. This is roughly 1.5 times higher than the normal operating pressure of 16 MPa. The initial phase of the operation saw the water temperature inside the primary circuit reach 135°C. The Automated Process Control System (APCS) was actively brought into operation during the tests to monitor safety and design compliance.
Completing the cold hydraulic tests clears the path for the final move toward electricity generation. The subsequent commissioning milestones before the reactor can go online include:
- Hot functional tests (simulating operational conditions at higher temperatures and pressures);
- Reactor plant overhaul and equipment adjustments;
- Nuclear fuel loading; and
- Reaching first criticality and obtaining the final operational licence.
Rosatom and Turkish officials aim to begin official launch operations by the end of 2026. “During the construction of Akkuyu unit 1, thousands of complex engineering operations were completed,” said Rosatom Director General Alexey Likhachev. “We are now at a stage where the results of this enormous work are being comprehensively tested. The safe operation of the entire power unit depends on the reliability of the primary circuit. There are extremely high technological requirements for equipment, pipelines, and welded joints. Hydraulic tests have been successfully completed. This is convincing confirmation of the quality of installation, welding, adjustment work –and is another step towards the physical start-up of the power unit.”
The plant will eventually host four Russian-designed VVER-1200 reactors. The pouring of first concrete for unit 1 took place in April 2018, for unit 2 in June 2020, for unit 3 in March 2021, and for unit 4 in July 2022. Rosatom is constructing the reactors according to a build-own-operate model. Work continues at the facilities of all four units and auxiliary structures as well as a new town for plant operators.