Cranes support new phase at PFSP

14 June 2022



Cleanup work at Sellafield’s legacy ponds required two enhanced handling systems to reach hard-to-access areas, and to avoid potential collisions with existing lifting equipment.


THE PILE FUEL STORAGE PONDS (PFSP) at Sellafield are among the most challenging nuclear decommissioning projects in Europe. Following the completion of a key stage in the removal of larger solid wastes from the ponds, a new dewatering and descaling project can now begin.

The project requires two handling systems to reach hard-to-access parts of the PFSP’s structure, and to avoid potential collisions with existing lifting equipment.

Procured for Sellafield via Cumbria Nuclear Solutions (CNSL), SCX Special Projects engineered two single girder cranes, each tailored to the ponds’ existing infrastructure and the task of enabling the next phase of decommissioning at the PFSP facility. A 2t MOTS (Modified Off The Shelf) crane with a bespoke extending, cantilevered bridge reaches into the numerous recesses along the pond’s wall. And a 4t COTS+ (Commercial Off-The-Shelf) crane equipped with collision avoidance technology shares the same rails as the existing 12t pond crane.

Speaking about the background to the project Stuart Robson, technical sales engineer, SCX, says Sellafield established the Decommissioning Delivery Partnership (DDP) in 2016 as a framework to deliver its substantial decommissioning and land remediation challenge. Originally planned to run for five years, in 2021 the DDP was extended by a further five years to 2026.

“The DDP is split into three Lots – Lots 2 and 3 focus on Magnox waste and swarf storage, while Lot 1 brings together two Pile Fuel facilities along with general site remediation and associated decommissioning work,” he adds.

“Lot 1 contains three consortia — one of which is Cumbria Nuclear Solutions Limited (CNSL), a collaboration of six specialist nuclear businesses. One of the primary facilities in Lot 1 is called the Pile Fuel Storage Pond (PFSP) — this is among the most challenging nuclear decommissioning projects in Europe. PFSP had recently been emptied of larger solid wastes, completing an important phase in its decommissioning journey. Now the challenge is to descale and dewater the ponds. Led
by consortium member Westinghouse, CNSL went to market in late 2018 with a requirement for ‘PFSP Enhanced Mechanical Handling’ — in essence, two enhanced and modified cranes to help carry out the required lifting and handling associated with the next phase in the project. SCX was awarded the contract to design and supply the cranes in May 2019.”

Robson says the project progressed smoothly, and the modified cranes were designed, engineered, and assembled at SCX’s facilities in Sheffield during 2020. They passed Factory Acceptance Tests in late 2020 and were delivered to site and commissioned in summer 2021.

The requirements for the two cranes differed in complexity: the smaller 2t crane needed an extending, cantilevered bridge to reach into the various recesses of the PFSP, which meant significant mechanical and electrical upgrades to a standard COTS crane.

The second 4t crane needed an anti-collision system, given that it shares rails with an existing crane. However, mechanically it remains a relatively standard overhead travelling crane.

“Sellafield has its own exacting standards for electrical wiring and labelling, so all electrical upgrades were engineered and commissioned to meet those,” adds Robson. He continues: “SCX has teams of mechanical, electrical and TU¨V-certified safety design engineers that work together to create a solution that: satisfies the client’s functionality and budget, ensures the safety of the people working with the system, and is practical to build and install.

“SCX’s experience in modifying commercial-off-the-shelf cranes goes back decades, and many of our solutions for the demanding nuclear sector have been designed and built this way. Using COTS equipment as the basis of a nuclear handling solution makes sense, because that equipment is already proven in industry. There’s no sense in reinventing the wheel and going bespoke — we always consider what we can do with existing, readily available and proven equipment first. If it’s not possible to deliver a fit-for-purpose system using the COTS/MOTS route, that’s when we explore the bespoke route.

A spokesman for CNSL says: “The project ran smoothly thanks to the good working relationships between all parties. The design and manufacture was undertaken professionally by SCX, and when minor issues arose — to be expected in the development of bespoke handling solutions — they were resolved quickly and to our satisfaction. The challenge of Covid was unavoidable, however it was accommodated well, and solutions to any problems were found in a timely manner.” 


First published in the January 2022 issue of Hoist. Sign up here for your free digital subscription: https://www2.ns-mediagroup.com/hoist-digital

The PFSP pond The PFSP pond
The 2t crane cantilevered bridge in operation The 2t crane cantilevered bridge in operation
The 4t crane during testing The 4t crane during testing
The 4t crane panel The 4t crane panel


Privacy Policy
We have updated our privacy policy. In the latest update it explains what cookies are and how we use them on our site. To learn more about cookies and their benefits, please view our privacy policy. Please be aware that parts of this site will not function correctly if you disable cookies. By continuing to use this site, you consent to our use of cookies in accordance with our privacy policy unless you have disabled them.