Sellafield Ltd fined after contractors inhale radioactive contamination

7 December 2009


Sellafield Ltd has been fined GBP75,000 ($123,000) after pleading guilty to breaches of health and safety law after two contractors inhaled radioactive contamination.

The prosecution follows an investigation by the Health and Safety Executive (HSE) into an incident on 11 July 2007 at Sellafield Nuclear Licensed Site in Cumbria.

Sellafield Ltd pleaded guilty to breaching Section 3(1) of the Health and Safety at Work etc Act 1974. The company was fined GBP75,000 and ordered to pay costs of GBP26,100 at Carlisle Crown Court.

The incident happened while removing radioactive contamination from an area of concrete floor in a room formerly used to sort and monitor material contaminated with plutonium. A patch of concrete floor – believed to be contaminated with radiation from spillage some years ago – was being drilled prior to being removed.

Two contractors were drilling an area of the floor, under Sellafield Ltd’s supervision, when they were contaminated with plutonium by the dust produced from the drilling, some of which they inhaled. There was no immediate impact on their health, but they received a significant radiation dose below annual dose limits.

The two workers were monitored, undressed and removed from the enclosure. One contractor had widespread contamination on his PVC suit and while he was undressing two radiation air monitors outside the enclosed area were triggered. The enclosure was later found to be heavily contaminated.

Mark Bassett, HSE’s Superintending Nuclear Inspector, said: “Although the radiation doses in this case were below the statutory dose limits, they could potentially have been higher. They should have been zero. The incident highlights the importance of Sellafield Ltd following its own arrangements for protecting workers, when undertaking potentially hazardous work with the risk of exposure to radiation. Sellafield Ltd should have properly assessed those risks, and then appropriately planned, organised and carried out the work.

“We are satisfied that Sellafield Ltd is taking the appropriate measures to improve both its arrangements and to ensure they are carried out properly. We will continue to monitor closely to ensure that these are implemented.”


Related Articles
Official figures show scale of Sellafield MOX Plant losses
Macro economics of uranium and plutonium
Nuclear in the UK – where did it go wrong?
Plute options
Sellafield MOX plant to continue operating


External weblinks
Nuclear Engineering International is not responsible for the content of external internet sites.

Video demonstration of MOXSIM
Nukenomics: The Commercialisation of Britain's Nuclear Industry



Privacy Policy
We have updated our privacy policy. In the latest update it explains what cookies are and how we use them on our site. To learn more about cookies and their benefits, please view our privacy policy. Please be aware that parts of this site will not function correctly if you disable cookies. By continuing to use this site, you consent to our use of cookies in accordance with our privacy policy unless you have disabled them.