Works resume at Kudankulam nuclear plant

28 March 2012


Work has resumed on India’s Kudankulam nuclear power plant, after a five-month interruption, Russian contractor Atomstroyexport has announced.

Work at the site was suspended in October 2011 as a result of protesters blocking access to the site. At that time commissioning of unit 1 was underway and hot testing had recently been completed.

According to Atomstoryexport a second phase of inspection work is currently being carried out in an effort to obtain a permit for fuel loading from the Atomic Energy Regulatory Board (AERB). Reports in the Indian press indicate that fuel loading could begin in a month or two.

Neither Atomstoryexport nor Nuclear Power Corporation of India (NPCIL) had given an expected date of operation for Kudankulam 1&2. However, according to NPCIL’s website unit 1 was 99.2% complete and unit 2 was 94.6% complete as of February 2012.

The prolonged protests against the Kudankulam nuclear plant have proved costly for the project, adding around $180 million to the total cost, according to reports in the Times of India.




Privacy Policy
We have updated our privacy policy. In the latest update it explains what cookies are and how we use them on our site. To learn more about cookies and their benefits, please view our privacy policy. Please be aware that parts of this site will not function correctly if you disable cookies. By continuing to use this site, you consent to our use of cookies in accordance with our privacy policy unless you have disabled them.