TEPCO begins pumping out unit 2 turbine building

19 April 2011


On 19 April TEPCO began pumping high-level radioactive water from the basement of the Fukushima Daiichi unit 2 turbine building to the centralised radiation waste treatment facility.

Reactor-by-reactor, system-by-system summary from JAIF as of 18 April
Reactor-by-reactor, system-by-system summary from JAIF as of 18 April; yellow indicates abnormal/unstable; red means damaged/nonfunctional


The process of pumping the water out, which was discovered in late March, was delayed to allow for several operations: the purging of 10,000 tons of low-level waste already in the facility, into the sea; inspection of the store building for cracks; installation of leakage barriers including silt fences, steel panels and caesium-absorbing zeolite sandbags in the unit 1-4 water intake and outflow area; and government approval of the plans. The TEPCO report to the government included the necessity of the operation, a safety assessment, and plans for permanent water storage and treatment facilities.

According to the Japan Atomic Industrial Forum, the unit 2 basement and external tunnel alone contains 25,000 tons of water. Transferring just 10,000 tons of it is expected to take 26 days.


Robot enters Unit 3
Packbot working inside the reactor building of Fukushima Daiichi Nuclear Power Station Unit 3

Also, following surveys of units 1 and 3, a remote-controlled robot entered and surveyed the unit 2 reactor building.




Privacy Policy
We have updated our privacy policy. In the latest update it explains what cookies are and how we use them on our site. To learn more about cookies and their benefits, please view our privacy policy. Please be aware that parts of this site will not function correctly if you disable cookies. By continuing to use this site, you consent to our use of cookies in accordance with our privacy policy unless you have disabled them.