RPV welded for unit 1 of Bangladesh nuclear power plant

14 May 2020


The reactor pressure vessel for Rooppur 1, a VVER-1200 (Photo: Atomenergomash)The Volgodonsk branch of AEM Technologies had completed the closing weld that connected the two halves of the reactor pressure vessel (RPV) being manufactured for unit 1 of the Rooppur nuclear power plant in Bangladesh.

Atomenergomash is the engineering division of Russia's state nuclear corporation, Rosatom.

The operation lasted for ten days with continuous heating of the weld zone - from 150 to 300 degrees Celsius. During this time, about two tons of flux and more than one and a half tons of wire were used.

After welding, the RPV weighing 320 tons will be heated to 300 degrees and, using a crane, will be transferred to the furnace for two days of heat treatment.

The next stage will be quality control operations including x-ray flaw detection, ultrasound and capillary control inspections.

AEM Technologies is manufacturing the internals for the RPV, as well as the reactor lid and the upper block.

Atomenergomash is the supplier of all the equipment for the reactor compartment of Rooppur NPP and a significant part of the equipment for the machine room.

Rosatom is building two 1200MWe VVER-1200 units at Rooppur, which is on the eastern bank of the river Ganges.


The reactor pressure vessel for Rooppur 1, a VVER-1200 (Photo: Atomenergomash)



Privacy Policy
We have updated our privacy policy. In the latest update it explains what cookies are and how we use them on our site. To learn more about cookies and their benefits, please view our privacy policy. Please be aware that parts of this site will not function correctly if you disable cookies. By continuing to use this site, you consent to our use of cookies in accordance with our privacy policy unless you have disabled them.