Reactor structure replaced in single piece

23 February 2005


Mitsubishi Heavy Industries Ltd replaced the internal structure of a reactor vessel at the No. 1 reactor at Shikoku Electric Power Co's Ikata power station in Ehime Prefecture, Japan, in one single piece.

The 100 tonne stainless steel structure that was replaced consists of a lower part housing the fuel assemblies and an upper part supporting them and is 8m in length with an internal diameter of 2.8m. The gap between the structure and the vessel measures 0.4mm at the narrowest part. A specially developed remote-control system was used for precision positioning.

The work would have taken about 200 days if dividing or cutting the structure had been involved. MHI completed the task in 70 days by extracting the whole structure from the vessel and placing it in a container.




Privacy Policy
We have updated our privacy policy. In the latest update it explains what cookies are and how we use them on our site. To learn more about cookies and their benefits, please view our privacy policy. Please be aware that parts of this site will not function correctly if you disable cookies. By continuing to use this site, you consent to our use of cookies in accordance with our privacy policy unless you have disabled them.