Nuclear power station construction work, Sellafield, UK (Deadline: 23 November 2009)

5 November 2009


Scope of work comprises the Design, Detail Design, Procurement, Construction, Delivery and Commissioning of Fellside Boiler Park. The proposed Contract shall comprise a number of phases as follows:

Phase 1 - Initial phase will be due diligence of assessment and design work, preparation of construction and commissioning phase plan, define and agree the Target Date and the total of the Prices.

Phase 2A will be general support up to sanction, procurement, design and advanced construction works.

Phase 2B will be Construction, Commissioning, Training Operators, Final test and completing documentation.

Phase 3 will be Learning from Experience (LFE), Call-off support.

Estimated value excluding VAT:

Range: between 4 000 000 and 8 000 000 GBP.

Contact:

Sellafield Ltd, Risley, Contact: Mrs Jill Andrews, UK-Warrington WA3 6AS. Tel. +44 1925836473. E-mail: jill.andrews@sellafieldsites.com. Fax +44 1925833497.


Related Articles
Westinghouse joins Cumbria Nuclear Solutions partnership



Privacy Policy
We have updated our privacy policy. In the latest update it explains what cookies are and how we use them on our site. To learn more about cookies and their benefits, please view our privacy policy. Please be aware that parts of this site will not function correctly if you disable cookies. By continuing to use this site, you consent to our use of cookies in accordance with our privacy policy unless you have disabled them.