NRC delays rulings on early site permits

18 August 2005


The US Nuclear Regulatory Commission (NRC) has delayed planned rulings on whether three utilities have the right to build new nuclear reactors at existing plants.

The NRC is extending the review schedules for the three early site permit (ESP) applications received in late 2003 after an unexpected volume of comments on environmental impact statements (EIS) and other factors.

NRC staff plan to finalise the review of the North Anna site in Louisa county, Virginia, by late December, about four months later than originally scheduled. The review of the Grand Gulf site near Vicksburg, Mississippi, should be finalised by mid-April 2006, also about four months later than first planned and the review of the Clinton site near Clinton, Illinois, should be completed by late July 2006, about nine months later than planned.

Public comments on the draft EIS for the North Anna ESP were much more numerous than anticipated when the NRC allocated resources for ESP reviews. The number of public comments on draft statements for the Clinton and Grand Gulf ESP sites also exceeded expectations.

If an ESP is granted, the applicant has up to 20 years to decide whether to build a new nuclear unit on the site and to file an application with the NRC for approval to begin construction.


Related Articles
Ontario's nuclear future
Two restarts for Bruce Power, but partner Cameco opts out



Privacy Policy
We have updated our privacy policy. In the latest update it explains what cookies are and how we use them on our site. To learn more about cookies and their benefits, please view our privacy policy. Please be aware that parts of this site will not function correctly if you disable cookies. By continuing to use this site, you consent to our use of cookies in accordance with our privacy policy unless you have disabled them.