This contract concerns the supply, the installation and appropriate software for: 23 whole body contamination monitors and 1 dummy whole body contamination monitor to control the personnel for surface or intern radioactive contaminations before leaving the controlled area of nuclear facility.

Detailed studies (documentation, drawings and calculations) must be provided.

The delivery and the replacing of the equipment shall be done during 2011, 2012 and 2013.

Contact:

Tractebel Engineering SA

Avenue Ariane, 7

Attn: Mrs. Bénédicte Walschaerts

1200 Brussels

BELGIUM

Tel. +32 27738651

E-mail: benedicte.walschaerts@gdfsuez.com

Fax +32 27738900

Internet: www.tractebel-engineering-gdfsuez.com

LOT NO: 1 TITLE Tihange 3

1)SHORT DESCRIPTION

1) Delivery and installation of whole body contamination monitors for the Tihange 3 unit;

2) 7 whole body contamination monitors divided over 4 dressing rooms;

3) Installation of the different lots depends on the plant outage schedule. Tractebel Engineering retains the right to change the time schedule in function of the plant outage.

LOT NO: 2 TITLE Tihange 2 + DCE

1)SHORT DESCRIPTION

1) Delivery and installation of whole body contamination monitors for the Tihange 2 unit and the DCE building;

2) Tihange 2: 5 whole body contamination monitors divided over 2 dressing rooms.

DCE: 3 whole body contamination monitors divided over 2 dressing rooms.

3) Installation of the different lots depends on the plant outage schedule. Tractebel Engineering retains the right to change the time schedule in function of the plant outage.

LOT NO: 3 TITLE Tihange 1 + Accès + CFN

1)SHORT DESCRIPTION

1) Delivery and installation of whole body contamination monitors for the Tihange 1 unit, access building and formation center;

2) Tihange 1: 6 whole body contamination monitors divided over 3 dressing rooms;

Access building: 2 whole body contamination monitors at the entrance.

CFN: 1 dummy body contamination monitor for the training center.

3) Installation of the different lots depends on the plant outage schedule. Tractebel Engineering retains the right to change the time schedule in function of the plant outage.




Privacy Policy
We have updated our privacy policy. In the latest update it explains what cookies are and how we use them on our site. To learn more about cookies and their benefits, please view our privacy policy. Please be aware that parts of this site will not function correctly if you disable cookies. By continuing to use this site, you consent to our use of cookies in accordance with our privacy policy unless you have disabled them.