Hot testing completed at Pakistan’s Karachi 2

10 September 2020


Unit 2 at Karachi nuclear power plant in Pakistan (Photo: Official WeChat account of CNNC]Unit 2 at Pakistan’s Karachi Nuclear Power Plant has completed hot functional tests, according to China National Nuclear Corporation (CNNC), which is constructing two units (2&3) at the plant.

Karachi 2 is the first overseas unit to use China's Hualong One technology. The thermal testing will be followed by nuclear fuel loading, grid connection and power generation.

The tests, lasting several weeks, includes simulating nuclear power plant operations to verify reliability of the main equipment and systems under thermal conditions before the reactor is loaded with nuclear fuel. They were completed on 4 September, CNNC said. Cold functional tests were completed at Karachi 2 in December 2019.

After the completion of hot tests, the Karachi 2 came close to the stage of physical launch, the message says.

Construction of the 1100MW Hualong One reactor Karachi 2 began in August 2015, followed by Karachi 3 in May 2016. 

The outer containment dome of the Karachi 3 was installed at the end of August, CNNC said.


Photo: Unit 2 Karachi nuclear power plant in Pakistan. [Photo: official WeChat account of CNNC]



Privacy Policy
We have updated our privacy policy. In the latest update it explains what cookies are and how we use them on our site. To learn more about cookies and their benefits, please view our privacy policy. Please be aware that parts of this site will not function correctly if you disable cookies. By continuing to use this site, you consent to our use of cookies in accordance with our privacy policy unless you have disabled them.