First mobile intermediate-level waste solidification plant

3 August 2003


BNFL Environmental Services has actively commissioned the first mobile waste solidification plant to process intermediate-level waste (ILW) in the UK. The Transportable ILW Solidification Plant (TILWSP) was designed and built specifically to process sludges and ion exchange resins at any of the UK's nuclear power plants.

The mobile unit is currently engaged on its first job at Trawsfynydd, where it is being used to process radioactive sludge.

TILWSP is able to process and package waste into standard Nirex containers. The waste sludges and resins are handled as a slurry and put into a 3m3 drum, where they are dewatered and then solidified in a cement-based matrix. The product is then checked for quality before the containers are capped off with an inactive grout and lidded. These packages are remotely handled and put into shielded overpacks and removed from the processing plant. They are then deposited into a packaged waste store on site.



Privacy Policy
We have updated our privacy policy. In the latest update it explains what cookies are and how we use them on our site. To learn more about cookies and their benefits, please view our privacy policy. Please be aware that parts of this site will not function correctly if you disable cookies. By continuing to use this site, you consent to our use of cookies in accordance with our privacy policy unless you have disabled them.