First concrete for Summer AP1000

11 March 2013


The 6-foot thick concrete basemat that forms the foundation of the containment and buildings within the nuclear island was completed at 10 am on 11 March 2013, South Carolina Electric & Gas Company (SCE&G) announced in a statement. The concrete pour covered an area of 32,000 square feet and took a total of 51.5 hours.

SCE&G and Santee Cooper are planning to build two 1117 MW Westinghouse AP1000 reactors at the existing VC Summer site in South Carolina. The reactors are slated to start-up in 2017 and 2018, respectively.

"This is an exciting achievement for SCE&G, Santee Cooper, CB&I, Westinghouse Electric Company, and others who support our new nuclear project," said Kevin Marsh, chairman and CEO of SCANA, the parent company of SCE&G.

 


Photo courtesy SCANA. Caption: Work on the V.C. Summer Unit 2 basemat went on throughout the night as crews continuously poured concrete into the rebar cages for 51 and a half hours.

 



Privacy Policy
We have updated our privacy policy. In the latest update it explains what cookies are and how we use them on our site. To learn more about cookies and their benefits, please view our privacy policy. Please be aware that parts of this site will not function correctly if you disable cookies. By continuing to use this site, you consent to our use of cookies in accordance with our privacy policy unless you have disabled them.