Eight new reactors by 2015

30 October 2001


South Korea’s utilities estimate demand for baseload electricity to grow at 2% per year, requiring 1500MWe per year of new capacity to be commissioned. A third of this is expected to be nuclear, involving eight more reactors by 2015, in addition to the four that are currently under construction.

Yonggwang 5 and 6 are due for completion next year, with Ulchin 5 and 6 in 2004/5. All four PWRs are 1000MWe Korean Standard Nuclear Plants (KSNPs). The next planned units are to be two improved KSNPs at Shin-Kori and two at Shin-Wolsong (see NEI July 2001, p8).

The first of the advanced PWR designs are due to be commissioned soon after, two at Shin-Kori and two at a new location adjacent to Ulchin. Korea Hydro & Nuclear Power (KHNP) say that the first two APR-1400 units at Shin-Kori will cost between $1300 and $1400 per kilowatt. Later reactors in the series are predicted to be $1200/kW and a construction time of 48 months.

Development of the APR began in late 1992, based on ABB-CE’s System 80+. The reactor has US design certification, but has never been built.



Privacy Policy
We have updated our privacy policy. In the latest update it explains what cookies are and how we use them on our site. To learn more about cookies and their benefits, please view our privacy policy. Please be aware that parts of this site will not function correctly if you disable cookies. By continuing to use this site, you consent to our use of cookies in accordance with our privacy policy unless you have disabled them.