China completes hot tests at Fuqing 4

12 May 2017


Hot testing was completed on 7 May at unit 4 of China’s Fuqing NPP under construction in Fujian province. Project owner China National Nuclear Corporation (CNNC) said completion of hot testing paves the way for fuel loading and the start of the reactor commissioning phase.

Construction of the 1087MWe Fuqing 4, a domestic Generation II CPR-1000 pressurised water reactor unit, began in November 2012.

The tests, which started on 25 March, were completed three days ahead of schedule. CNNC said the CPR-1000 pressurised water reactor, scheduled to start up later this year, has now officially entered the fuel loading stage.



Privacy Policy
We have updated our privacy policy. In the latest update it explains what cookies are and how we use them on our site. To learn more about cookies and their benefits, please view our privacy policy. Please be aware that parts of this site will not function correctly if you disable cookies. By continuing to use this site, you consent to our use of cookies in accordance with our privacy policy unless you have disabled them.