A major safety investment programme at Barsebäck 2 will continue as planned, despite political moves to limit the reactor's operating life.

The programme includes the replacement of primary systems. More than $10 million will be spent annually over the next three years on the programme, which will include emptying the reactor vessel of water for the first time since operations began in 1977. Barsebäck plant manager Leif Ost is confident that the reactor "would remain productive for many years."



Privacy Policy
We have updated our privacy policy. In the latest update it explains what cookies are and how we use them on our site. To learn more about cookies and their benefits, please view our privacy policy. Please be aware that parts of this site will not function correctly if you disable cookies. By continuing to use this site, you consent to our use of cookies in accordance with our privacy policy unless you have disabled them.