ARCADIS to provide consultancy for Angra 3

27 May 2014


Brazil-based ARCADIS Logos has won a EUR21 million contract from Eletrobras Termonuclear to provide engineering consulting services for the Angra 3 nuclear power plant under construction in the state of Rio de Janeiro.

The scope of work to be performed over the 36-month contract includes technical services during completion of the plant as well as monitoring of inspection and testing.

At the peak of the activities, ARCADIS says that 70 of its professionals will be active on the jobsite.

ARCADIS Logos has worked at the Angra site since the early 1970s, when it provided construction management services for Angra 1. In 2010, the company returned to provide project management and technical support to Eletrobras during the implementation of Angra 3.

Last November, AREVA signed a contract worth EUR 1.25 billion for the completion of the construction for the 1405 MW Angra 3 pressurised water reactor. The reactor is expected to be completed by 2018.


Photo: Angra 1 nuclear power plant



Privacy Policy
We have updated our privacy policy. In the latest update it explains what cookies are and how we use them on our site. To learn more about cookies and their benefits, please view our privacy policy. Please be aware that parts of this site will not function correctly if you disable cookies. By continuing to use this site, you consent to our use of cookies in accordance with our privacy policy unless you have disabled them.