Alstom finishes Ringhals 3 turbine I&C refit

6 January 2011


Power generation equipment supplier Alstom has completed the installation of a new control system for block 3 of the Ringhals nuclear power plant in only 30 days.

The system has passed a series of operational testing since Ringhals 3 first synchronized to the grid in mid-October.

This is the last important milestone of the integrated retrofit of the complete turbo group systems of block 3 at Ringhals. The commissioning of the new control system enabled the plant to deliver full power output in time for the increasing winter demand.

After a long period of engineering and mock-up tests the actual installation work began in late August and was completed one month later, to meet the deadline for cold commissioning – a phase of preparation, installation and testing, before turning the reactor steam on.

The next major step for Alstom is the completion of block 4 in 2011, which includes installation of the control system, erection of four new moisture separators, installation of two high-pressure turbines and two low-pressure preheaters.

The Ringhals nuclear power plant is situated on the west coast of Sweden 60 kilometres south of Gothenburg. The plant has four reactors - three pressurised water reactors and one boiling water reactor. In a normal year, Ringhals generates around 28 billion kilowatt-hours of electricity – approximately one fifth of Sweden’s total electrical energy consumption – and sufficient to supply six cities the size of Gothenburg with electricity. The plant’s total power output is about 3690 MW.




Privacy Policy
We have updated our privacy policy. In the latest update it explains what cookies are and how we use them on our site. To learn more about cookies and their benefits, please view our privacy policy. Please be aware that parts of this site will not function correctly if you disable cookies. By continuing to use this site, you consent to our use of cookies in accordance with our privacy policy unless you have disabled them.